Energy Projects Near You

Solar, wind and battery projects near Llanidloes (SY18)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY18 (Powys): 2 are waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Llandinam Windfarm Repowering and Extension (102 MW wind farm, approved on 7 September 2015, not yet built; REPD status may be out of date), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
3approved, not running
3operational

Projects within 10 km of SY18

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bryn Posteg Landfill Site Solar Array & Battery Storagesolar farmsolar farm1abandonedupdated Nov 2021Jun 2022—Nov 2021Powys2.4
Bryn Blaen Wind Farmwind farmwind farm13.8operationalupdated Feb 2024Dec 2014granted Aug 2016Feb 2024Powys3.9
Hirddywelwind farmwind farm27application submitted may be out of dateupdated Oct 2017Jun 2010—Oct 2017Powys7.2
Llandinam Windfarmwind farmwind farm31operationalupdated Dec 2009——Dec 2009Powys8.0
Bryn titli Windfarmwind farmwind farm9.9operationalupdated Oct 2018Mar 1993granted Aug 1993Oct 2018Powys8.4
Hirddywell Windfarmwind farmwind farm14.8application withdrawnupdated Jun 2011Aug 2000—Jun 2011Powys8.6
Llandinam Windfarm Repowering and Extensionwind farmwind farm102approved, not built may be out of dateupdated Jun 2020May 2008granted Sep 2015Jun 2020Powys8.6
Waun Garnowind farmwind farm16.5refusedupdated Mar 2012Apr 2008refused Mar 2012Mar 2012Powys9.6
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bryn Posteg Landfill Site Solar Array & Battery Storagebattery storagebattery storage—abandonedupdated Jul 2022Jun 2022—Jul 2022Powys2.4
Glynhafren, Old Hallwind turbinewind turbine—application submittedupdated Mar 2026Mar 2026—Mar 2026Powys6.2
Plas Trannon, Trefeglwyssolar farmsolar farm0.6approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025Powys7.1
Meadow Springs Country & Leisure Park, Ffinnantsolar farmsolar farm0.9approved, not builtupdated Jan 2026Aug 2025granted Dec 2025Jan 2026Powys8.5

Distance from the average position of the SY18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm302001.5
Wind farm71131129
Wind turbine110000
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY18, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.