Energy Projects Near You

Solar, wind and battery projects near Llanbrynmair (SY19)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY19 (Powys): 2 approved but not yet running, 5 operational. The largest live scheme is Carno 3 (45 MW wind farm, approved on 26 May 2017, not yet built; REPD status may be out of date), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
2approved, not running
5operational

Projects within 10 km of SY19

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cemmaes 3 Wind Farmwind farmwind farm24appeal withdrawnupdated Nov 2015Feb 2008refused Jan 2013Nov 2015Powys0.1
Carno 'B' Wind Farmwind farmwind farm16.8operationalupdated Oct 2011Dec 1993granted Aug 1995Oct 2011Powys3.8
Carno 3wind farmwind farm45approved, not built may be out of dateupdated Dec 2025Jul 2010granted May 2017Dec 2025Powys5.5
Carno 'A' Wind Farmwind farmwind farm16.8operationalupdated Oct 2011Aug 1993granted Aug 1995Oct 2011Powys5.6
Carno 'A'and 'B' Wind Farm, (Extension)wind farmwind farm15.6operationalupdated Jan 2010Oct 2003granted Jul 2006Jan 2010Powys5.6
Cemmaes 'C' Wind Farmwind farmwind farm15.3operationalupdated Sep 2010Oct 2000granted Apr 2001Sep 2010Powys7.3
Waun Garnowind farmwind farm16.5refusedupdated Mar 2012Apr 2008refused Mar 2012Mar 2012Powys8.4
Nant Carfan Wind Farmwind farmwind farm20.8refusedupdated Dec 2003Apr 1999refused May 2002Dec 2003Powys8.9
Cemmaes 'B' Wind Farmwind farmwind farm3.4operationalupdated Feb 2010Sep 1996granted Mar 1999Feb 2010Powys9.1
Esgair Cwmowenwind farmwind farm51application withdrawnupdated Sep 2014Dec 2003—Sep 2014Powys9.5
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rallt Carno Solar Arrayssolar farmsolar farm0.2approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Powys3.9

Distance from the average position of the SY19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Wind farm10015245

MW in pipeline: pending, approved and under-construction capacity.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY19, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.