Carno 'B' Wind Farm (16.8 MW)

Carno 'B' Wind Farm is a 16.8 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 1996; the record was last updated on 30 October 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.8 MWwind farm
operationalstatus in REPD
30 October 2011record last updated
Powyscouncil area

Planning timeline

DateStage
30 December 1993Application submitted
18 August 1995Planning permission granted
1 October 1996Operational

Project details

Technology
wind farm
Capacity
16.8 MW
Status (REPD)
operational
Record last updated
30 October 2011
Operator or applicant
RWE npower
Planning authority
Powys
Planning application reference
not recorded
Turbines
28
Address (REPD)
Trannon Moor, Carno, Powys
Council area (by location)
Powys
Time to decision
85 weeks
REPD reference
2564

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carno 'A' Wind Farmwind farm16.8operational2.1
Carno 'A'and 'B' Wind Farm, (Extension)wind farm15.6operational2.1
Carno 3wind farm45approved, not built3.6
Cemmaes 3 Wind Farmwind farm24appeal withdrawn3.7
Waun Garnowind farm16.5refused5.1
Esgair Cwmowenwind farm51application withdrawn8.6
Mynydd Yr Hendre Wind Farmwind farm29.1refused9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5494, -3.6082).