Carno 'A'and 'B' Wind Farm, (Extension) (15.6 MW)

Carno 'A'and 'B' Wind Farm, (Extension) is a 15.6 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2009; the record was last updated on 6 January 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.6 MWwind farm
operationalstatus in REPD
6 January 2010record last updated
Powyscouncil area

Planning timeline

DateStage
10 October 2003Application submitted
10 July 2006Planning permission granted
1 March 2009Operational

Project details

Technology
wind farm
Capacity
15.6 MW
Status (REPD)
operational
Record last updated
6 January 2010
Operator or applicant
RWE npower
Planning authority
Powys
Planning application reference
M2003/1156
Turbines
12
Address (REPD)
Cwm Cledan , Carno , Powys
Council area (by location)
Powys
Time to decision
143 weeks
REPD reference
3277

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carno 'A' Wind Farmwind farm16.8operational<0.1
Carno 'B' Wind Farmwind farm16.8operational2.1
Carno 3wind farm45approved, not built2.5
Waun Garnowind farm16.5refused3.0
Cemmaes 3 Wind Farmwind farm24appeal withdrawn5.5
Esgair Cwmowenwind farm51application withdrawn7.4
Mynydd Yr Hendre Wind Farmwind farm29.1refused9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5423, -3.5792).