Mynydd Yr Hendre Wind Farm (29.1 MW)
Mynydd Yr Hendre Wind Farm is a 29.1 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 May 2002; the record was last updated on 10 March 2003.
29.1 MWwind farm
refusedstatus in REPD
10 March 2003record last updated
Powyscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 1 February 1999 | Application submitted |
| 23 May 2002 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 29.1 MW
- Status (REPD)
- refused
- Record last updated
- 10 March 2003
- Operator or applicant
- RWE npower
- Planning authority
- Powys
- Planning application reference
- not recorded
- Address (REPD)
- Mynydd Yr Hendre Cefn Coch Newton Powys
- Council area (by location)
- Powys
- Time to decision
- 172 weeks
- REPD reference
- 2579
Who decides
| Applications | Powys | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 42 | 10,236 |
| Refused | 15 (36%) | 19% |
| Solar refused | 2 of 15 | 12% |
| Onshore wind refused | 12 of 24 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 78.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Tirgwynt | wind farm | 24.6 | operational | 1.2 |
| Esgair Cwmowen | wind farm | 51 | application withdrawn | 2.0 |
| Mynydd Waun Fawr Wind Farm | wind farm | 37.5 | application withdrawn | 4.2 |
| Mynydd Clogau Wind Farm - Extension | wind farm | 16 | application withdrawn | 4.9 |
| Mynydd Clogau Wind Farm | wind farm | 14.5 | operational | 4.9 |
| Carno 3 | wind farm | 45 | approved, not built | 6.5 |
| Esgair Cwmowen | wind farm | 47.5 | application submitted | 7.7 |
| Carno 'A' Wind Farm | wind farm | 16.8 | operational | 9.0 |
| Carno 'A'and 'B' Wind Farm, (Extension) | wind farm | 15.6 | operational | 9.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6019, -3.4898).