Energy Projects Near You

Solar, wind and battery projects near Machynlleth (SY20)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY20 (Powys): 1 is waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Glandulas Mawr Farm (0.3 MW solar farm, approved on 28 June 2019, not yet built; REPD status may be out of date), 0.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
1awaiting a decision
1approved, not running
1operational

Projects within 10 km of SY20

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Braich Dduwind farmwind farm3.9operationalupdated Oct 2013Mar 2004granted Sep 2004Oct 2013Gwynedd9.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Aberffrydlan, Llanwrinwind turbinewind turbine—application submittedJun 2026——Powys0.7
Glandulas Mawr Farmsolar farmsolar farm0.3approved, not built may be out of dateupdated Jun 2024Mar 2019granted Jun 2019Jun 2024Powys0.8

Distance from the average position of the SY20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.3
Wind farm100100
Wind turbine110000

MW in pipeline: pending, approved and under-construction capacity.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY20, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.