Solar, wind and battery projects near Tywyn (LL36)
3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL36 (Gwynedd): 2 operational. The largest scheme is Braich Ddu (3.9 MW wind farm, operational since 31 August 2007), 7.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LL36
Projects of 1 MW and more (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Land at Morfa Campsolar farm | solar farm | 2.8 | operationalupdated Aug 2016 | Jul 2015 | granted Oct 2015 | Aug 2016 | Gwynedd | 2.8 |
| Braich Dduwind farm | wind farm | 3.9 | operationalupdated Oct 2013 | Mar 2004 | granted Sep 2004 | Oct 2013 | Gwynedd | 7.2 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Llanfendigaid, Rhoslefainsolar farm | solar farm | 0.1 | abandonedupdated Sep 2023 | Dec 2022 | refused Apr 2023 | Sep 2023 | Gwynedd | 4.2 |
Distance from the average position of the LL36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 0 | 0 | 1 | 0 | 0 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Gwynedd decides solar, wind and battery applications
| Applications | Gwynedd | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 6 (32%) | 19% |
| Solar refused | 3 of 13 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.