Renewable energy projects in Gwynedd

22 solar, wind or battery projects of 150 kW or more are located in Gwynedd (REPD, July 2026 extract): 4 pending, 5 approved but not running, 6 operational and 4 refused. The council refused 6 of 19 decided applications (32%; UK 19%), with a median 17 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects in the council area
4awaiting a decision
5approved, not running
32%of decisions refused

How Gwynedd decides

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Gwynedd

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Tyddyn Forgan, Llanddeiniolenbattery storagebattery storage100approved, not builtupdated Feb 2026Apr 2025granted Jan 2026Feb 2026
Seion, Pentirbattery storagebattery storage99.9refusedupdated Mar 2026Apr 2025refused Jan 2026Mar 2026
Gaerwen Wind Farmwind farmwind farm59.4application submittedupdated Oct 2025Jul 2025—Oct 2025
Pentir Substation, Pentirbattery storagebattery storage57approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024
Parciau Farm Solar Parksolar farmsolar farm13.9operationalupdated Sep 2015Jun 2014granted Sep 2014Sep 2015
Bodelith Isaf Wind Turbineswind farmwind farm5refusedupdated Nov 2015Apr 2014refused Oct 2015Nov 2015
Llwyndyrys Farmsolar farmsolar farm5permission expiredupdated Mar 2020Aug 2015granted Nov 2015Mar 2020
Nanhoron Estatesolar farmsolar farm5abandonedupdated Oct 2019Nov 2015granted Nov 2016Oct 2019
Land off Lon Pin, Llanbedrog Solar Farmsolar farmsolar farm5refusedupdated Nov 2025Dec 2023refused Oct 2025Nov 2025
Tyddyn Cae (Nefyn)solar farmsolar farm4.9operationalupdated Dec 2015Sep 2014granted Feb 2015Dec 2015
Ty Du Uchaf, Pentreuchafsolar farmsolar farm4.8application submitted may be out of dateupdated Sep 2024Jul 2024—Sep 2024
Fferm Bryn Bachausolar farmsolar farm4.4operationalupdated Dec 2017Jul 2015granted Sep 2015Dec 2017
Braich Dduwind farmwind farm3.9operationalupdated Oct 2013Mar 2004granted Sep 2004Oct 2013
Tyddyn Gwyn (Gelli Gron Farm)solar farmsolar farm3.8operationalupdated May 2017Jul 2015granted Nov 2015May 2017
Land at Morfa Campsolar farmsolar farm2.8operationalupdated Aug 2016Jul 2015granted Oct 2015Aug 2016
Land on Park Farmsolar farmsolar farm2.4refusedupdated Nov 2015Jul 2015refused Nov 2015Nov 2015
Rehau Plastics, Pencefn Roadrooftop solarrooftop solar1approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Derwin Fawr Wind Turbines Replacementwind farmwind farm0.8application submittedupdated Nov 2025Sep 2025—Nov 2025
Caernarfon Road Solar Panelsrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2021Nov 2020granted Apr 2021Feb 2021
Nanhoron Home Farm, Nanhoronrooftop solarrooftop solar0.2approved, not builtupdated Aug 2022Jul 2022granted Aug 2022Aug 2022
Llanfendigaid, Rhoslefainsolar farmsolar farm0.1abandonedupdated Sep 2023Dec 2022refused Apr 2023Sep 2023
Gaerwen Wind Farmbattery storagebattery storage—application submittedupdated Oct 2025Jul 2025—Oct 2025

Postcode districts in Gwynedd

DistrictProjects within 10 kmPendingApprovedOperational
LL231000
LL353002
LL363002
LL372001
LL381000
LL390000
LL400000
LL411010
LL420000
LL430000
LL440000
LL450000
LL460000
LL470000
LL481010
LL490000
LL514102
LL523102
LL536111
LL542100
LL556031
LL568231
LL578051

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Gwynedd by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.