Energy Projects Near You

Solar, wind and battery projects near Caernarfon (LL55)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL55 (Gwynedd): 3 approved but not yet running, 1 operational. The largest live scheme is Tyddyn Forgan, Llanddeiniolen (100 MW battery storage, approved on 23 January 2026, not yet built), 6.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
3approved, not running
1operational

Projects within 10 km of LL55

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Parciau Farm Solar Parksolar farmsolar farm13.9operationalupdated Sep 2015Jun 2014granted Sep 2014Sep 2015Gwynedd4.3
Tyddyn Forgan, Llanddeiniolenbattery storagebattery storage100approved, not builtupdated Feb 2026Apr 2025granted Jan 2026Feb 2026Gwynedd6.3
Seion, Pentirbattery storagebattery storage99.9refusedupdated Mar 2026Apr 2025refused Jan 2026Mar 2026Gwynedd6.3
Pentir Substation, Pentirbattery storagebattery storage57approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Gwynedd6.5
Land on Park Farmsolar farmsolar farm2.4refusedupdated Nov 2015Jul 2015refused Nov 2015Nov 2015Gwynedd8.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Caernarfon Road Solar Panelsrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2021Nov 2020granted Apr 2021Feb 2021Gwynedd8.8

Distance from the average position of the LL55 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200110
Rooftop solar101000.4
Battery storage30201157

MW in pipeline: pending, approved and under-construction capacity.

How Gwynedd decides solar, wind and battery applications

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Gwynedd

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL55, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.