Energy Projects Near You

Seion, Pentir (99.9 MW battery storage)

Seion, Pentir is a 99.9 MW battery storage project in Gwynedd, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 January 2026; the record was last updated on 25 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
refusedstatus in REPD
25 March 2026record last updated
Gwyneddcouncil area

Planning timeline

DateStage
8 April 2025Application submitted
23 January 2026Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
refused
Record last updated
25 March 2026
Operator or applicant
Brockwell Storage & Solar Limited
Planning authority
Gwynedd
Planning application reference
C25/0277/18/LL
Address (REPD)
S/O B4547 Seion, Pentir, Llanddeiniolen, Caernarfon
Council area (by location)
Gwynedd
Time to decision
41 weeks
Name in REPD
Seion, Pentir - Battery Energy Storage System
REPD reference
18711

Who decides

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tyddyn Forgan, Llanddeiniolenbattery storage100approved, not built<0.1
Pentir Substation, Pentirbattery storage57approved, not built0.5
Parciau Farm Solar Parksolar farm13.9operational5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1859, -4.1666).