Energy Projects Near You

Tyddyn Forgan, Llanddeiniolen (100 MW battery storage)

Tyddyn Forgan, Llanddeiniolen is a 100 MW battery storage project in Gwynedd, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 January 2026, not yet built; the record was last updated on 24 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
24 February 2026record last updated
Gwyneddcouncil area

Planning timeline

DateStage
3 April 2025Application submitted
23 January 2026Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
24 February 2026
Operator or applicant
Firstway Energy / Net Zero Twenty Six Limited
Planning authority
Gwynedd
Planning application reference
C25/0266/18/LL
Address (REPD)
Tyddyn Forgan, Llanddeiniolen, Caernarfon
Council area (by location)
Gwynedd
Time to decision
42 weeks
Name in REPD
Tyddyn Forgan, Llanddeiniolen - Energy Storage System
REPD reference
18370

Who decides

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Seion, Pentirbattery storage99.9refused<0.1
Pentir Substation, Pentirbattery storage57approved, not built0.5
Parciau Farm Solar Parksolar farm13.9operational5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1859, -4.1666).