Energy Projects Near You

Solar, wind and battery projects near Menai Bridge (LL59)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL59 (Isle of Anglesey): 2 are waiting for a planning decision, 6 approved but not yet running, 1 operational. The largest live scheme is Solar Farm & Energy Storage Facility (160 MW solar farm, approved on 26 August 2025, not yet built), 6.4 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Awel y Mor Offshore Wind Farm (775 MW, approved, not built), 34.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
6approved, not running
1operational

Projects within 10 km of LL59

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Braint Wind Farmwind farmwind farm2.6refusedupdated Sep 2016Aug 2013refused Jul 2015Sep 2016Isle of Anglesey3.6
Tyddyn Forgan, Llanddeiniolenbattery storagebattery storage100approved, not builtupdated Feb 2026Apr 2025granted Jan 2026Feb 2026Gwynedd5.5
Seion, Pentirbattery storagebattery storage99.9refusedupdated Mar 2026Apr 2025refused Jan 2026Mar 2026Gwynedd5.5
Pentir Substation, Pentirbattery storagebattery storage57approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Gwynedd5.6
Solar Farm & Energy Storage Facilitysolar farmsolar farm160approved, not builtupdated Oct 2025May 2024granted Aug 2025Oct 2025Isle of Anglesey6.4
Parciau Farm Solar Parksolar farmsolar farm13.9operationalupdated Sep 2015Jun 2014granted Sep 2014Sep 2015Gwynedd9.5
Prysan Wind Farmwind farmwind farm9.9refusedupdated Apr 2005Dec 1995refused Aug 1996Apr 2005Isle of Anglesey9.7
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Caernarfon Road Solar Panelsrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2021Nov 2020granted Apr 2021Feb 2021Gwynedd3.3
Solar Farm & Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Oct 2025May 2024granted Aug 2025Oct 2025Isle of Anglesey6.4
M-SParcsolar farmsolar farm0.9application submittedupdated Apr 2026Mar 2026—Apr 2026Isle of Anglesey6.9
M-SParcbattery storagebattery storage0.4application submittedupdated Apr 2026Mar 2026—Apr 2026Isle of Anglesey6.9
W O Jones Printers Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024Isle of Anglesey9.9

Distance from the average position of the LL59 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm31110161
Rooftop solar101000.4
Wind farm200020
Battery storage61401158

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202634.9
Rhyl Flats90operationalupdated Aug 201738.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Isle of Anglesey decides solar, wind and battery applications

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Anglesey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL59, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.