Energy Projects Near You

Prysan Wind Farm (9.9 MW)

Prysan Wind Farm is a 9.9 MW wind farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 August 1996; the record was last updated on 13 April 2005.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWwind farm
refusedstatus in REPD
13 April 2005record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
18 December 1995Application submitted
6 August 1996Refused by the planning authority

Project details

Technology
wind farm
Capacity
9.9 MW
Status (REPD)
refused
Record last updated
13 April 2005
Operator or applicant
South Western Power / Renewable Energy Systems (RES) / NOVERA
Planning authority
Isle of Anglesey
Planning application reference
not recorded
Address (REPD)
Prysan Farm, Rhuddlan, Bach, Llanddyfnan, Anglesey
Council area (by location)
Isle of Anglesey
Time to decision
33 weeks
REPD reference
2578

Who decides

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farm24application submitted6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2954, -4.2671).