Solar, wind and battery projects near Llangefni (LL77)
11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL77 (Isle of Anglesey): 5 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storage (24 MW wind farm, application submitted on 30 September 2025, no decision recorded), 1.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LL77
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farm | wind farm | 24 | application submittedupdated Dec 2025 | Sep 2025 | — | Dec 2025 | Isle of Anglesey | 1.8 |
| Prysan Wind Farmwind farm | wind farm | 9.9 | refusedupdated Apr 2005 | Dec 1995 | refused Aug 1996 | Apr 2005 | Isle of Anglesey | 4.9 |
| Cefn Cae Forsolar farm | solar farm | 5 | permission expiredupdated Sep 2018 | Sep 2015 | granted Feb 2016 | Sep 2018 | Isle of Anglesey | 6.4 |
| Bryn yr Odyn Solar Farmsolar farm | solar farm | 15 | operationalupdated Apr 2015 | Sep 2013 | granted Nov 2013 | Apr 2015 | Isle of Anglesey | 6.9 |
| Braint Wind Farmwind farm | wind farm | 2.6 | refusedupdated Sep 2016 | Aug 2013 | refused Jul 2015 | Sep 2016 | Isle of Anglesey | 7.2 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cyngor Sir Ynys Monrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Jan 2024 | Jan 2024 | Isle of Anglesey | 0.9 |
| W O Jones Printers Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2024 | Jun 2024 | granted Aug 2024 | Sep 2024 | Isle of Anglesey | 1.0 |
| Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagebattery storage | battery storage | — | application submittedupdated Dec 2025 | Sep 2025 | — | Dec 2025 | Isle of Anglesey | 1.8 |
| M-SParcsolar farm | solar farm | 0.9 | application submittedupdated Apr 2026 | Mar 2026 | — | Apr 2026 | Isle of Anglesey | 5.1 |
| M-SParcbattery storage | battery storage | 0.4 | application submittedupdated Apr 2026 | Mar 2026 | — | Apr 2026 | Isle of Anglesey | 5.1 |
| Hafod Y Gyfnessolar farm | solar farm | 0.5 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Isle of Anglesey | 5.5 |
Distance from the average position of the LL77 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 2 | 0 | 1 | 0 | 1.4 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.5 |
| Wind farm | 3 | 1 | 0 | 0 | 2 | 24 |
| Battery storage | 3 | 2 | 1 | 0 | 0 | 0.6 |
MW in pipeline: pending, approved and under-construction capacity.
How Isle of Anglesey decides solar, wind and battery applications
| Applications | Isle of Anglesey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 0 of 5 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in Isle of Anglesey
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.