Bryn yr Odyn Solar Farm (15 MW)
Bryn yr Odyn Solar Farm is a 15 MW solar farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2015; the record was last updated on 16 April 2015.
15 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Isle of Angleseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 September 2013 | Application submitted |
| 6 November 2013 | Planning permission granted |
| 6 November 2014 | Construction started |
| 28 February 2015 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 15 MW
- Status (REPD)
- operational
- Record last updated
- 16 April 2015
- Operator or applicant
- New Forest Energy Ltd
- Planning authority
- Isle of Anglesey
- Planning application reference
- 10C118A/RE
- Site area
- 30.0 ha
- Address (REPD)
- Bryn yr Odyn
- Council area (by location)
- Isle of Anglesey
- Time to decision
- 8 weeks
- REPD reference
- 2353
Who decides
| Applications | Isle of Anglesey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 0 of 5 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Cefn Cae For | solar farm | 5 | permission expired | 1.5 |
| Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storage | wind farm | 24 | application submitted | 5.1 |
| Bodorgan Solar Farm | solar farm | 12.6 | operational | 6.1 |
| Parc Solar Traffwll | solar farm | 35 | approved, not built | 6.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2333, -4.4047).