Bryn yr Odyn Solar Farm (15 MW)

Bryn yr Odyn Solar Farm is a 15 MW solar farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2015; the record was last updated on 16 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
8 September 2013Application submitted
6 November 2013Planning permission granted
6 November 2014Construction started
28 February 2015Operational

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
16 April 2015
Operator or applicant
New Forest Energy Ltd
Planning authority
Isle of Anglesey
Planning application reference
10C118A/RE
Site area
30.0 ha
Address (REPD)
Bryn yr Odyn
Council area (by location)
Isle of Anglesey
Time to decision
8 weeks
REPD reference
2353

Who decides

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cefn Cae Forsolar farm5permission expired1.5
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farm24application submitted5.1
Bodorgan Solar Farmsolar farm12.6operational6.1
Parc Solar Traffwllsolar farm35approved, not built6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2333, -4.4047).