Energy Projects Near You

Bodorgan Solar Farm (12.6 MW)

Bodorgan Solar Farm is a 12.6 MW solar farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 June 2014; the record was last updated on 1 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.6 MWsolar farm
operationalstatus in REPD
1 October 2014record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
15 November 2012Application submitted
9 February 2013Planning permission granted
15 September 2013Construction started
20 June 2014Operational

Project details

Technology
solar farm
Capacity
12.6 MW
Status (REPD)
operational
Record last updated
1 October 2014
Operator or applicant
Anesco
Planning authority
Isle of Anglesey
Planning application reference
10C114A
Site area
30.0 ha
Address (REPD)
Tai Moelion farm near Aberffraw, Anglesey
Council area (by location)
Isle of Anglesey
Time to decision
12 weeks
REPD reference
2104

Who decides

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bryn yr Odyn Solar Farmsolar farm15operational6.1
Cefn Cae Forsolar farm5permission expired7.6
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farm24application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1787, -4.4148).