Parc Solar Traffwll (35 MW)

Parc Solar Traffwll is a 35 MW solar farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 March 2023, not yet built; the record was last updated on 11 May 2023. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
approved, not builtstatus in REPD
11 May 2023record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
18 February 2022Application submitted
17 March 2023Planning permission granted
17 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
11 May 2023
Operator or applicant
Low Carbon
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3217391
Site area
62.7 ha
Address (REPD)
Land to the West of Llanfihangel yn Nhowyn and to the South West of Bryngwran
Council area (by location)
Isle of Anglesey
Time to decision
56 weeks
Contracts for Difference
AR5
REPD reference
7471

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cefn Cae Forsolar farm5permission expired5.8
Bryn yr Odyn Solar Farmsolar farm15operational6.5
Penrhos Worksbattery storage349approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2644, -4.488).