Energy Projects Near You

Solar, wind and battery projects near Holyhead (LL65)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL65 (Isle of Anglesey): 2 approved but not yet running, 1 operational. The largest live scheme is Penrhos Works (349 MW battery storage, approved on 24 January 2024, not yet built), 1.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
2approved, not running
1operational

Projects within 10 km of LL65

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Penrhos Worksbattery storagebattery storage349approved, not builtupdated Feb 2024Nov 2023granted Jan 2024Feb 2024Isle of Anglesey1.9
Parc Solar Traffwllsolar farmsolar farm35approved, not builtupdated May 2023Feb 2022granted Mar 2023May 2023Isle of Anglesey6.8
Llanbabo Wind Farmwind farmwind farm20.4operationalupdated Jun 2005Aug 1994granted Dec 1996Jun 2005Isle of Anglesey9.1

Distance from the average position of the LL65 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1010035
Wind farm100100
Battery storage10100349

MW in pipeline: pending, approved and under-construction capacity.

How Isle of Anglesey decides solar, wind and battery applications

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Anglesey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.