Llanbabo Wind Farm (20.4 MW)
Llanbabo Wind Farm is a 20.4 MW wind farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 1997; the record was last updated on 4 June 2005.
20.4 MWwind farm
operationalstatus in REPD
4 June 2005record last updated
Isle of Angleseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 August 1994 | Application submitted |
| 19 December 1996 | Planning permission granted |
| 1 October 1997 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 20.4 MW
- Status (REPD)
- operational
- Record last updated
- 4 June 2005
- Operator or applicant
- MANWEB Generation Holdings
- Planning authority
- Isle of Anglesey
- Planning application reference
- not recorded
- Turbines
- 9
- Address (REPD)
- Llanbabo Wind Farm Land tp the north of Llyn Alaw Isle of Anglesey Gwynedd
- Council area (by location)
- Isle of Anglesey
- Time to decision
- 124 weeks
- REPD reference
- 2582
Who decides
| Applications | Isle of Anglesey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 0 of 5 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Carrog Ganol, Rhosgoch | battery storage | 300 | approved, not built | 5.3 |
| Porth Wen | solar farm | 49.9 | under construction | 6.4 |
| Rhyd-y-Groes Wind Farm - repowering | wind farm | 9.9 | approved, not built | 7.2 |
| Trysglwyn Wind Farm | wind farm | 5.6 | operational | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3544, -4.4656).