Carrog Ganol, Rhosgoch (300 MW battery storage)

Carrog Ganol, Rhosgoch is a 300 MW battery storage project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 September 2024, not yet built; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
approved, not builtstatus in REPD
31 March 2026record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
15 August 2023Application submitted
26 September 2024Planning permission granted
26 September 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Boom Developments Limited
Planning authority
Isle of Anglesey
Planning application reference
FPL/2023/218
Address (REPD)
Carrog Ganol, Rhosgoch
Council area (by location)
Isle of Anglesey
Time to decision
58 weeks
Name in REPD
Carrog Ganol, Rhosgoch - Battery Energy Storage System
REPD reference
13217

Who decides

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Porth Wensolar farm49.9under construction1.5
Rhyd-y-Groes Wind Farm - repoweringwind farm9.9approved, not built2.8
Llanbabo Wind Farmwind farm20.4operational5.3
Trysglwyn Wind Farmwind farm5.6operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3998, -4.4412).