Energy Projects Near You

Trysglwyn Wind Farm (5.6 MW)

Trysglwyn Wind Farm is a 5.6 MW wind farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 1996; the record was last updated on 9 December 2003.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWwind farm
operationalstatus in REPD
9 December 2003record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
8 August 1992Application submitted
10 December 1993Planning permission granted
1 May 1996Operational

Project details

Technology
wind farm
Capacity
5.6 MW
Status (REPD)
operational
Record last updated
9 December 2003
Operator or applicant
RWE npower
Planning authority
Isle of Anglesey
Planning application reference
not recorded
Turbines
14
Address (REPD)
Trysglwyn Fawr Rhosybol Isle of Anglesey Gwynedd
Council area (by location)
Isle of Anglesey
Time to decision
70 weeks
REPD reference
2567

Who decides

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rhyd-y-Groes Wind Farm - repoweringwind farm9.9approved, not built5.1
Porth Wensolar farm49.9under construction6.0
Carrog Ganol, Rhosgochbattery storage300approved, not built6.9
Llanbabo Wind Farmwind farm20.4operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3748, -4.3465).