Trysglwyn Wind Farm (5.6 MW)
Trysglwyn Wind Farm is a 5.6 MW wind farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 1996; the record was last updated on 9 December 2003.
5.6 MWwind farm
operationalstatus in REPD
9 December 2003record last updated
Isle of Angleseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 August 1992 | Application submitted |
| 10 December 1993 | Planning permission granted |
| 1 May 1996 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 5.6 MW
- Status (REPD)
- operational
- Record last updated
- 9 December 2003
- Operator or applicant
- RWE npower
- Planning authority
- Isle of Anglesey
- Planning application reference
- not recorded
- Turbines
- 14
- Address (REPD)
- Trysglwyn Fawr Rhosybol Isle of Anglesey Gwynedd
- Council area (by location)
- Isle of Anglesey
- Time to decision
- 70 weeks
- REPD reference
- 2567
Who decides
| Applications | Isle of Anglesey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 0 of 5 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Rhyd-y-Groes Wind Farm - repowering | wind farm | 9.9 | approved, not built | 5.1 |
| Porth Wen | solar farm | 49.9 | under construction | 6.0 |
| Carrog Ganol, Rhosgoch | battery storage | 300 | approved, not built | 6.9 |
| Llanbabo Wind Farm | wind farm | 20.4 | operational | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3748, -4.3465).