Solar, wind and battery projects near Cemaes Bay (LL67)
7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL67 (Isle of Anglesey): 3 approved but not yet running, 3 operational. The largest live scheme is Carrog Ganol, Rhosgoch (300 MW battery storage, approved on 26 September 2024, not yet built), 1.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LL67
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Carrog Ganol, Rhosgochbattery storage | battery storage | 300 | approved, not builtupdated Mar 2026 | Aug 2023 | granted Sep 2024 | Mar 2026 | Isle of Anglesey | 1.6 |
| Porth Wensolar farm | solar farm | 49.9 | under constructionupdated Jul 2022 | Mar 2016 | granted Mar 2018 | Jul 2022 | Isle of Anglesey | 2.5 |
| Rhyd-y-Groes Wind Farm - repoweringwind farm | wind farm | 9.9 | approved, not built may be out of dateupdated Mar 2020 | Apr 2015 | granted Oct 2016 | Mar 2020 | Isle of Anglesey | 3.7 |
| Ysgellog 2 Wind Farmwind farm | wind farm | 4.6 | refusedupdated Dec 2014 | Mar 2014 | refused Jan 2015 | Dec 2014 | Isle of Anglesey | 4.2 |
| Ystgellog Farm Wind Farmwind farm | wind farm | 4.6 | operationalupdated May 2013 | Oct 2010 | granted Jun 2011 | May 2013 | Isle of Anglesey | 4.2 |
| Llanbabo Wind Farmwind farm | wind farm | 20.4 | operationalupdated Jun 2005 | Aug 1994 | granted Dec 1996 | Jun 2005 | Isle of Anglesey | 6.3 |
| Trysglwyn Wind Farmwind farm | wind farm | 5.6 | operationalupdated Dec 2003 | Aug 1992 | granted Dec 1993 | Dec 2003 | Isle of Anglesey | 8.4 |
Distance from the average position of the LL67 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 49.9 |
| Wind farm | 5 | 0 | 1 | 3 | 1 | 9.9 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 300 |
MW in pipeline: pending, approved and under-construction capacity.
How Isle of Anglesey decides solar, wind and battery applications
| Applications | Isle of Anglesey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 0 of 5 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in Isle of Anglesey
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL67, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.