Energy Projects Near You

Solar, wind and battery projects near Cemaes Bay (LL67)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL67 (Isle of Anglesey): 3 approved but not yet running, 3 operational. The largest live scheme is Carrog Ganol, Rhosgoch (300 MW battery storage, approved on 26 September 2024, not yet built), 1.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
3approved, not running
3operational

Projects within 10 km of LL67

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Carrog Ganol, Rhosgochbattery storagebattery storage300approved, not builtupdated Mar 2026Aug 2023granted Sep 2024Mar 2026Isle of Anglesey1.6
Porth Wensolar farmsolar farm49.9under constructionupdated Jul 2022Mar 2016granted Mar 2018Jul 2022Isle of Anglesey2.5
Rhyd-y-Groes Wind Farm - repoweringwind farmwind farm9.9approved, not built may be out of dateupdated Mar 2020Apr 2015granted Oct 2016Mar 2020Isle of Anglesey3.7
Ysgellog 2 Wind Farmwind farmwind farm4.6refusedupdated Dec 2014Mar 2014refused Jan 2015Dec 2014Isle of Anglesey4.2
Ystgellog Farm Wind Farmwind farmwind farm4.6operationalupdated May 2013Oct 2010granted Jun 2011May 2013Isle of Anglesey4.2
Llanbabo Wind Farmwind farmwind farm20.4operationalupdated Jun 2005Aug 1994granted Dec 1996Jun 2005Isle of Anglesey6.3
Trysglwyn Wind Farmwind farmwind farm5.6operationalupdated Dec 2003Aug 1992granted Dec 1993Dec 2003Isle of Anglesey8.4

Distance from the average position of the LL67 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1010049.9
Wind farm501319.9
Battery storage10100300

MW in pipeline: pending, approved and under-construction capacity.

How Isle of Anglesey decides solar, wind and battery applications

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Anglesey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL67, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.