Penrhos Works (349 MW battery storage)

Penrhos Works is a 349 MW battery storage project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 January 2024, not yet built; the record was last updated on 27 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

349 MWbattery storage
approved, not builtstatus in REPD
27 February 2024record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
27 November 2023Application submitted
24 January 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
349 MW
Status (REPD)
approved, not built
Record last updated
27 February 2024
Operator or applicant
Anglesey Land Holdings Limited
Planning authority
Isle of Anglesey
Planning application reference
OP/2023/8
Address (REPD)
Penrhos Works, Holyhead
Council area (by location)
Isle of Anglesey
Time to decision
8 weeks
Name in REPD
Penrhos Works - Battery Energy Storage System
REPD reference
15472

Who decides

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parc Solar Traffwllsolar farm35approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2948, -4.597).