Energy Projects Near You

Solar, wind and battery projects near Brynteg (LL78)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL78 (Isle of Anglesey): 3 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storage (24 MW wind farm, application submitted on 30 September 2025, no decision recorded), 8.7 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Awel y Mor Offshore Wind Farm (775 MW, approved, not built), 34.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
3awaiting a decision
2approved, not running
1operational

Projects within 10 km of LL78

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Prysan Wind Farmwind farmwind farm9.9refusedupdated Apr 2005Dec 1995refused Aug 1996Apr 2005Isle of Anglesey2.5
Braint Wind Farmwind farmwind farm2.6refusedupdated Sep 2016Aug 2013refused Jul 2015Sep 2016Isle of Anglesey8.0
Trysglwyn Wind Farmwind farmwind farm5.6operationalupdated Dec 2003Aug 1992granted Dec 1993Dec 2003Isle of Anglesey8.4
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farmwind farm24application submittedupdated Dec 2025Sep 2025—Dec 2025Isle of Anglesey8.7
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
W O Jones Printers Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024Isle of Anglesey7.7
Cyngor Sir Ynys Monrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Isle of Anglesey7.8
Hafod Y Gyfnessolar farmsolar farm0.5application submittedupdated Sep 2025Aug 2025—Sep 2025Isle of Anglesey8.3
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagebattery storagebattery storage—application submittedupdated Dec 2025Sep 2025—Dec 2025Isle of Anglesey8.7

Distance from the average position of the LL78 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110000.5
Rooftop solar101000.5
Wind farm4101224
Battery storage211000.2

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202634.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Isle of Anglesey decides solar, wind and battery applications

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Anglesey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.