Energy Projects Near You

Solar, wind and battery projects near Marianglas (LL73)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL73 (Isle of Anglesey): 1 operational. The largest scheme is Prysan Wind Farm (9.9 MW wind farm, refused on 6 August 1996), 4.7 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Awel y Mor Offshore Wind Farm (775 MW, approved, not built), 32.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of LL73

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Prysan Wind Farmwind farmwind farm9.9refusedupdated Apr 2005Dec 1995refused Aug 1996Apr 2005Isle of Anglesey4.7
Trysglwyn Wind Farmwind farmwind farm5.6operationalupdated Dec 2003Aug 1992granted Dec 1993Dec 2003Isle of Anglesey8.1
Braint Wind Farmwind farmwind farm2.6refusedupdated Sep 2016Aug 2013refused Jul 2015Sep 2016Isle of Anglesey9.3

Distance from the average position of the LL73 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm300120

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202632.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Isle of Anglesey decides solar, wind and battery applications

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Anglesey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.