Energy Projects Near You

Solar, wind and battery projects near Pentraeth (LL75)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL75 (Isle of Anglesey): 4 are waiting for a planning decision, 5 approved but not yet running. The largest live scheme is Solar Farm & Energy Storage Facility (160 MW solar farm, approved on 26 August 2025, not yet built), 7.8 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Awel y Mor Offshore Wind Farm (775 MW, approved, not built), 34.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
4awaiting a decision
5approved, not running
0operational

Projects within 10 km of LL75

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Braint Wind Farmwind farmwind farm2.6refusedupdated Sep 2016Aug 2013refused Jul 2015Sep 2016Isle of Anglesey3.5
Prysan Wind Farmwind farmwind farm9.9refusedupdated Apr 2005Dec 1995refused Aug 1996Apr 2005Isle of Anglesey3.5
Solar Farm & Energy Storage Facilitysolar farmsolar farm160approved, not builtupdated Oct 2025May 2024granted Aug 2025Oct 2025Isle of Anglesey7.8
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farmwind farm24application submittedupdated Dec 2025Sep 2025—Dec 2025Isle of Anglesey8.7
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
W O Jones Printers Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024Isle of Anglesey7.0
Cyngor Sir Ynys Monrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Isle of Anglesey7.1
M-SParcsolar farmsolar farm0.9application submittedupdated Apr 2026Mar 2026—Apr 2026Isle of Anglesey7.4
M-SParcbattery storagebattery storage0.4application submittedupdated Apr 2026Mar 2026—Apr 2026Isle of Anglesey7.4
Solar Farm & Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Oct 2025May 2024granted Aug 2025Oct 2025Isle of Anglesey7.8
Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagebattery storagebattery storage—application submittedupdated Dec 2025Sep 2025—Dec 2025Isle of Anglesey8.7
Caernarfon Road Solar Panelsrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2021Nov 2020granted Apr 2021Feb 2021Gwynedd9.7

Distance from the average position of the LL75 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm21100161
Rooftop solar202000.9
Wind farm3100224
Battery storage422000.6

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202634.0
Rhyl Flats90operationalupdated Aug 201739.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Isle of Anglesey decides solar, wind and battery applications

ApplicationsIsle of AngleseyUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused0 of 512%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Anglesey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL75, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.