Solar Farm & Energy Storage Facility (160 MW)

Solar Farm & Energy Storage Facility is a 160 MW solar farm project in Isle of Anglesey, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 August 2025, not yet built; the record was last updated on 2 October 2025. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

160 MWsolar farm
approved, not builtstatus in REPD
2 October 2025record last updated
Isle of Angleseycouncil area

Planning timeline

DateStage
16 May 2024Application submitted
26 August 2025Planning permission granted

Project details

Technology
solar farm
Capacity
160 MW
Status (REPD)
approved, not built
Record last updated
2 October 2025
Operator or applicant
Enso Energy Limited
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3274702
Site area
268.8 ha
Address (REPD)
Llyn Alaw, Beaumaris
Council area (by location)
Isle of Anglesey
Time to decision
67 weeks
Name in REPD
Alaw Môn Solar Farm - Solar Farm & Energy Storage Facility
REPD reference
9226

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.28, -4.099).