Energy Projects Near You

Solar, wind and battery projects near Llanfairfechan (LL33)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL33 (Conwy): 2 approved but not yet running. The largest live scheme is Solar Farm & Energy Storage Facility (160 MW solar farm, approved on 26 August 2025, not yet built), 8.6 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Rhyl Flats (90 MW, operational), 26.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of LL33

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Farm & Energy Storage Facilitysolar farmsolar farm160approved, not builtupdated Oct 2025May 2024granted Aug 2025Oct 2025Isle of Anglesey8.6
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Farm & Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Oct 2025May 2024granted Aug 2025Oct 2025Isle of Anglesey8.6

Distance from the average position of the LL33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10100160
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Rhyl Flats90operationalupdated Aug 201726.6
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202626.6
Gwynt y Mor576operationalupdated Aug 202032.5
North Hoyle60operationalupdated Aug 201739.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Conwy decides solar, wind and battery applications

ApplicationsConwyUK
Decided applications (solar, wind, battery)1210,236
Refused5 (42%)19%
Solar refused0 of 112%
Onshore wind refused5 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision31.3 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Conwy

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.