Energy Projects Near You

Gwynt y Mor offshore wind farm

Gwynt y Mor is a 576 MW offshore wind farm with 160 turbines in Welsh waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 June 2015; the record was last updated on 19 August 2020. Its REPD grid reference is 17 km from the nearest postcode on land (LL18 3YP, Denbighshire). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

576 MWoffshore wind farm
operationalstatus in REPD
19 August 2020record last updated
17 km from land (Denbighshire)REPD location

Consent timeline

DateStage
1 November 2005Application submitted
3 December 2008Section 36 consent granted (Secretary of State)
1 March 2012Construction started
18 June 2015Operational

Project details

Technology
offshore wind farm
Capacity
576 MW
Turbines
160
Turbine capacity
3.6 MW
Status (REPD)
operational
Record last updated
19 August 2020
Operator or applicant
RWE
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
LL18 3YP (Denbighshire), 17.0 km from the REPD grid reference
Time to decision
161 weeks
REPD reference
2543

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Rhyl (LL18)18.9
Colwyn Bay (LL29)19.1
Llandudno (LL30)19.7
Prestatyn (LL19)19.8
Colwyn Bay (LL28)20.6
Abergele (LL22)20.8
Llandudno Junction (LL31)21.9
St Asaph (LL17)25.7
Conwy (LL32)26.0
Penmaenmawr (LL34)27.9
Wirral (CH47)31.0
Holywell (CH8)31.6

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Rhyl Flats90operational8.5
Awel y Mor Offshore Wind Farm775approved, not built11.7
North Hoyle60operational12.5
Burbo Bank Extension (Burbo Bank 2)258operational23.8
Mona Offshore Wind Farm1,500approved, not built24.3
Burbo Bank90operational29.5

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.454, -3.6266).

From application to operation, Gwynt y Mor (in Welsh, Gwynt y Môr) took almost ten years, and consent took longest. The application was submitted on 1 November 2005; the Section 36 consent (the REPD record lists DECC as the decision-maker) came on 3 December 2008, after 161 weeks. The median for offshore wind is 95.8 weeks, so the farm waited more than one and a half times as long. Construction began on 1 March 2012, and the 160 turbines of 3.6 MW have been operational since 18 June 2015.

Neighbours off the north Wales coast

Two small early farms stand within 30 km of the farm's location: Rhyl Flats at 90 MW, 8.5 km away, and North Hoyle at 60 MW, 12.5 km away. Two large ones are approved, not built: Awel y Mor at 775 MW and Mona at 1,500 MW. The nearest onshore postcode districts are Rhyl and Llandudno. Statuses come from the July 2026 REPD extract; the register can lag behind decisions.