From application to operation, Gwynt y Mor (in Welsh, Gwynt y Môr) took almost ten years, and consent took longest. The application was submitted on 1 November 2005; the Section 36 consent (the REPD record lists DECC as the decision-maker) came on 3 December 2008, after 161 weeks. The median for offshore wind is 95.8 weeks, so the farm waited more than one and a half times as long. Construction began on 1 March 2012, and the 160 turbines of 3.6 MW have been operational since 18 June 2015.
Neighbours off the north Wales coast
Two small early farms stand within 30 km of the farm's location: Rhyl Flats at 90 MW, 8.5 km away, and North Hoyle at 60 MW, 12.5 km away. Two large ones are approved, not built: Awel y Mor at 775 MW and Mona at 1,500 MW. The nearest onshore postcode districts are Rhyl and Llandudno. Statuses come from the July 2026 REPD extract; the register can lag behind decisions.