Energy Projects Near You

Burbo Bank Extension (Burbo Bank 2) offshore wind farm

Burbo Bank Extension (Burbo Bank 2) is a 258 MW offshore wind farm with 32 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 April 2017; the record was last updated on 2 May 2018. Its REPD grid reference is 11 km from the nearest postcode on land (CH47 5AY, Wirral). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010026).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

258 MWoffshore wind farm
operationalstatus in REPD
2 May 2018record last updated
11 km from land (Wirral)REPD location

Consent timeline

DateStage
22 March 2013Application submitted
10 December 2014Development consent granted (Secretary of State)
10 June 2016Construction started
27 April 2017Operational

Project details

Technology
offshore wind farm
Capacity
258 MW
Turbines
32
Turbine capacity
8 MW
Status (REPD)
operational
Record last updated
2 May 2018
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010026
Nearest postcode on land
CH47 5AY (Wirral), 10.9 km from the REPD grid reference
Time to decision
90 weeks
Contracts for Difference
Investment Contract
REPD reference
2539

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010026). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Wirral (CH47)11.4
Wirral (CH46)13.5
Wirral (CH48)13.9
Liverpool (L38)15.3
Wallasey (CH45)15.5
Wirral (CH49)15.6
Liverpool (L22)16.0
Liverpool (L37)16.1
Liverpool (L23)16.4
Wallasey (CH44)17.0
Prenton (CH43)17.5
Liverpool (L21)17.9

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Burbo Bank90operational5.7
North Hoyle60operational13.7
Gwynt y Mor576operational23.8
Rhyl Flats90operational27.0

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.48, -3.27).