Energy Projects Near You

Solar, wind and battery projects near Wirral (CH49)

24 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CH49 (Wirral): 2 are waiting for a planning decision, 19 approved but not yet running, 1 operational. The largest live scheme is Huskisson Dock Building, Huskisson Dock (1.5 MW rooftop solar, approved on 8 March 2024, not yet built), 8.6 km away. Offshore, 5 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 13.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24projects within 10 km
2awaiting a decision
19approved, not running
1operational

Projects within 10 km of CH49

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Beaufort Roadbattery storagebattery storage20permission expiredupdated Apr 2020Sep 2016—Apr 2020Wirral4.4
Britannia Housebattery storagebattery storage10permission expiredupdated Oct 2023Sep 2017granted Dec 2017Oct 2023Wirral4.7
Burbo Bank Energy Storagebattery storagebattery storage2operationalupdated Feb 2020Apr 2017—Feb 2020Wirral4.8
Huskisson Dock Building, Huskisson Dockrooftop solarrooftop solar1.5approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Liverpool8.6
Smaller schemes under 1 MW, mostly rooftop solar (20)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodchurch High School, Carr Bridge Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2026Sep 2025granted Nov 2025Jan 2026Wirral1.9
Woodchurch High School, Carr Bridge Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Wirral1.9
Tesco, Bidston Link Road, Bidstonrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Wirral3.7
Tesco Pharmacy, Bidstonrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Feb 2026granted May 2026Jun 2026Wirral3.7
Valley Road, Bidstonrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Wirral3.8
Murrayfield Hospital, Holmwood Drivesolar farmsolar farm0.2approved, not built may be out of dateupdated Jul 2023Jan 2023granted Jun 2023Jul 2023Wirral3.9
Sainsburys, Woodchurch Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Wirral4.0
St Marys College, Wallasey Villagerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Wirral5.4
Tipographic, Morpeth Wharfrooftop solarrooftop solar0.8approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Wirral6.1
Port Of Liverpool Building, Mann Islandrooftop solarrooftop solar—approved, not builtupdated Jan 2026Dec 2025granted Feb 2026Jan 2026Liverpool7.7
Mercedes-Benz, Pall Mallrooftop solarrooftop solar0.3approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022Liverpool8.2
HMS Eaglet, Sefton Street Wind Turbine & Solar Panelsrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Liverpool8.2
HMS Eaglet, Sefton Street Wind Turbine & Solar Panelswind turbinewind turbine—application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Liverpool8.2
Biffa Waste Services, Dock Road South Battery Storage Unitsbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Wirral8.8
Bulk Powder Terminals, Regent Roadrooftop solarrooftop solar0.7approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Liverpool9.1
Temp Control Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton9.1
Steel Terminal, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Liverpool9.3
Tesco Superstorerooftop solarrooftop solar—approved, not builtupdated Mar 2021Jan 2021granted Apr 2021Mar 2021Liverpool9.3
Sainsburys, Jennifer Avenuerooftop solarrooftop solar0.5approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Liverpool9.5
Waste Care, Lower Bank Viewrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Liverpool9.6

Distance from the average position of the CH49 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Rooftop solar18117006
Wind turbine110000
Battery storage401100

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201813.1
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201815.6
North Hoyle60operationalupdated Aug 201723.2
Rhyl Flats90operationalupdated Aug 201735.6
Gwynt y Mor576operationalupdated Aug 202035.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Wirral decides solar, wind and battery applications

ApplicationsWirralUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 912%
Battery storage refused0 of 216%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Wirral

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CH49, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.