Burbo Bank, one of the first offshore wind farms off Liverpool, stands roughly 9 km from the Sefton coast. Its 25 turbines of 3.6 MW each are operated by Orsted (formerly Dong Energy), and from the project's point in the register, 12 Liverpool and Wirral postcode districts, including L38 and CH47, lie just 10–13 km away.
A long consent, a quick build
The application went in on 12 April 2002, but the Section 36 consent only arrived on 14 July 2006: 222 weeks against a median of 95.8 for offshore wind, more than twice as long. The register records the consenting authority as DECC, the energy ministry of the day. After that things moved fast: construction started on 1 August 2006, and on 18 October 2007 the wind farm became operational.
Extension and neighbours
At 5.7 km, Burbo Bank Extension is operational with 258 MW, a separate project far more powerful than the first phase's 90 MW. Further out, at 19–30 km, stand North Hoyle (60 MW) and Gwynt y Mor (576 MW). The Burbo Bank record was last updated on 27 February 2018; the figures come from the REPD extract for July 2026.