Energy Projects Near You

Solar, wind and battery projects near Liverpool (L37)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L37 (Sefton): 8 approved but not yet running, 1 operational. The largest live scheme is North Moss Lane Solar Photovoltaic Farm (9 MW solar farm, approved on 7 August 2025, not yet built), 2.4 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 11.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
0awaiting a decision
8approved, not running
1operational

Projects within 10 km of L37

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
North Moss Lane Solar Photovoltaic Farmsolar farmsolar farm9approved, not builtupdated Aug 2025Feb 2025granted Aug 2025Aug 2025Sefton2.4
Jemmys Carrsolar farmsolar farm5under constructionupdated Oct 2019Aug 2015granted Sep 2016Oct 2019Sefton2.8
Land at Tip Fieldsolar farmsolar farm5under constructionupdated Mar 2020Jul 2015granted Sep 2016Mar 2020West Lancashire3.1
Orrell Hillsolar farmsolar farm20refusedupdated Jul 2015Aug 2014refused Jun 2015Jul 2015Sefton3.7
Lower Alt Wind Farmwind farmwind farm42refusedupdated Apr 2017Dec 2015refused Nov 2016Apr 2017West Lancashire5.4
Fromby Lane Solar Farmsolar farmsolar farm5appeal withdrawnupdated Mar 2020Jul 2015refused Oct 2015Mar 2020West Lancashire8.3
Back Lane Solar Farmsolar farmsolar farm5appeal withdrawnupdated Aug 2018Jul 2015refused Oct 2015Aug 2018Sefton8.5
Lower House Farmsolar farmsolar farm1.9refusedupdated Jan 2016Jul 2015refused Dec 2015Jan 2016West Lancashire8.5
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Formby High Schoolrooftop solarrooftop solar0.4approved, not builtupdated May 2022Apr 2022granted Jun 2022May 2022Sefton0.6
Suttons Farm, Lord Sefton Wayrooftop solarrooftop solar0.5approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024West Lancashire2.4
Pawfect Retreat, Moor Farmrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Sefton4.0
Ainsdale Wastewater Treatment Workssolar farmsolar farm0.3operationalupdated Sep 2019Dec 2018granted Mar 2019Sep 2019Sefton4.5
Deyes Academy Redevelopmentrooftop solarrooftop solar0.6under constructionupdated Aug 2022Mar 2022granted Jun 2022Aug 2022Sefton9.5
Meadows Leisure Centre, Hall Lanerooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Sefton9.6

Distance from the average position of the L37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8031219
Rooftop solar505001.9
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201811.1
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201816.1
North Hoyle60operationalupdated Aug 201729.8
Gwynt y Mor576operationalupdated Aug 202039.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Sefton decides solar, wind and battery applications

ApplicationsSeftonUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused3 of 3312%
Onshore wind refused0 of 245%
Battery storage refused1 of 516%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Sefton

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.