Jemmys Carr (5 MW solar farm)

Jemmys Carr is a 5 MW solar farm project in Sefton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 22 September 2019; the record was last updated on 23 October 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
23 October 2019record last updated
Seftoncouncil area

Planning timeline

DateStage
3 August 2015Application submitted
23 September 2016Planning permission granted
22 September 2019Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
23 October 2019
Operator or applicant
Beacons Cross Solar (formerly Jemmys Carr Solar)
Planning authority
Sefton
Planning application reference
DC/2015/01266
Site area
7.3 ha
Address (REPD)
Land At Jemmy Carr, Field North Of Downholland Brook, Moss Lane, Formby
Council area (by location)
Sefton
Time to decision
60 weeks
REPD reference
5938

Who decides

ApplicationsSeftonUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused3 of 3312%
Onshore wind refused0 of 245%
Battery storage refused1 of 516%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Tip Fieldsolar farm5under construction0.4
North Moss Lane Solar Photovoltaic Farmsolar farm9approved, not built0.6
Lower Alt Wind Farmwind farm42refused4.8
Orrell Hillsolar farm20refused5.0
Fromby Lane Solar Farmsolar farm5appeal withdrawn6.3
Back Lane Solar Farmsolar farm5appeal withdrawn6.8
Gerard Hall Solar Farmsolar farm17refused on appeal9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5702, -3.0283).