North Moss Lane Solar Photovoltaic Farm (9 MW)

North Moss Lane Solar Photovoltaic Farm is a 9 MW solar farm project in Sefton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 August 2025, not yet built; the record was last updated on 26 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
approved, not builtstatus in REPD
26 August 2025record last updated
Seftoncouncil area

Planning timeline

DateStage
25 February 2025Application submitted
7 August 2025Planning permission granted
7 August 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Taiyo Power & Storage Limited
Planning authority
Sefton
Planning application reference
DC/2025/00299
Site area
14.6 ha
Address (REPD)
North Moss Farm, North Moss Lane, Liverpool
Council area (by location)
Sefton
Time to decision
23 weeks
Name in REPD
North Moss Lane - Solar Photovoltaic Farm
REPD reference
18292

Earlier applications for this site

ApplicationMWSubmittedOutcome
North Moss Lane Solar Photovoltaic Farm DC/2023/02024930 November 2023refused 31 May 2024

Who decides

ApplicationsSeftonUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused3 of 3312%
Onshore wind refused0 of 245%
Battery storage refused1 of 516%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jemmys Carrsolar farm5under construction0.6
Land at Tip Fieldsolar farm5under construction0.8
Orrell Hillsolar farm20refused5.1
Lower Alt Wind Farmwind farm42refused5.2
Fromby Lane Solar Farmsolar farm5appeal withdrawn6.9
Back Lane Solar Farmsolar farm5appeal withdrawn7.4
Gerard Hall Solar Farmsolar farm17refused on appeal9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5719, -3.0369).