Solar, wind and battery projects near Liverpool (L23)
60 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L23 (Sefton): 4 are waiting for a planning decision, 45 approved but not yet running, 3 operational. The largest live scheme is Hawthorne Road (20 MW battery storage, under construction), 4.3 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 10.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of L23
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Royal Seaforth Dock, New Jenkins Shedsrooftop solar | rooftop solar | 2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 2.7 |
| Royal Seaforth Dock Wind Farmwind farm | wind farm | 3 | operationalupdated Feb 2003 | Oct 1995 | granted Aug 1997 | Feb 2003 | Sefton | 3.1 |
| Orrell Hillsolar farm | solar farm | 20 | refusedupdated Jul 2015 | Aug 2014 | refused Jun 2015 | Jul 2015 | Sefton | 4.1 |
| Hawthorne Roadbattery storage | battery storage | 20 | under constructionupdated Sep 2020 | Jan 2020 | granted Mar 2022 | Sep 2020 | Sefton | 4.3 |
| Port of Liverpool windwind farm | wind farm | 10 | operationalupdated Jun 2010 | Aug 2005 | granted Dec 2005 | Jun 2010 | Sefton | 4.8 |
| Lower Alt Wind Farmwind farm | wind farm | 42 | refusedupdated Apr 2017 | Dec 2015 | refused Nov 2016 | Apr 2017 | West Lancashire | 5.0 |
| Huskisson Dock Building, Huskisson Dockrooftop solar | rooftop solar | 1.5 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Liverpool | 6.7 |
| Back Lane Solar Farmsolar farm | solar farm | 5 | appeal withdrawnupdated Aug 2018 | Jul 2015 | refused Oct 2015 | Aug 2018 | Sefton | 7.9 |
| Gerard Hall Solar Farmsolar farm | solar farm | 17 | refused on appealupdated Feb 2016 | Jun 2014 | refused Oct 2014 | Feb 2016 | West Lancashire | 8.4 |
| Jemmys Carrsolar farm | solar farm | 5 | under constructionupdated Oct 2019 | Aug 2015 | granted Sep 2016 | Oct 2019 | Sefton | 8.8 |
| Fromby Lane Solar Farmsolar farm | solar farm | 5 | appeal withdrawnupdated Mar 2020 | Jul 2015 | refused Oct 2015 | Mar 2020 | West Lancashire | 8.8 |
| D H L Exel Supply Chain Burton Foods, Portal Wayrooftop solar | rooftop solar | 1 | application submitted may be out of dateupdated Jul 2023 | Jun 2023 | — | Jul 2023 | Liverpool | 9.0 |
| North Moss Lane Solar Photovoltaic Farmsolar farm | solar farm | 9 | approved, not builtupdated Aug 2025 | Feb 2025 | granted Aug 2025 | Aug 2025 | Sefton | 9.0 |
| Burbo Bank Energy Storagebattery storage | battery storage | 2 | operationalupdated Feb 2020 | Apr 2017 | — | Feb 2020 | Wirral | 9.1 |
| Land at Tip Fieldsolar farm | solar farm | 5 | under constructionupdated Mar 2020 | Jul 2015 | granted Sep 2016 | Mar 2020 | West Lancashire | 9.1 |
| Britannia Housebattery storage | battery storage | 10 | permission expiredupdated Oct 2023 | Sep 2017 | granted Dec 2017 | Oct 2023 | Wirral | 9.5 |
| Beaufort Roadbattery storage | battery storage | 20 | permission expiredupdated Apr 2020 | Sep 2016 | — | Apr 2020 | Wirral | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (43)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| CWT North Building, Royal Seaforth Dockrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 2.7 |
| Briggs Marine, Langton Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Sefton | 2.7 |
| Maritime IT Building, Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Sefton | 2.7 |
| Royal Seaforth Dock, CWT Stores Buildingrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Sefton | 2.7 |
| Maritime Stores, Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Sefton | 2.7 |
| Rubies 1 Building, Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 2.7 |
| Rubies 2 Building, Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 2.7 |
| Rubies 3 Building, Royal Seaforth Dockrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Jan 2024 | Jan 2024 | — | Jan 2024 | Sefton | 2.8 |
| Royal Seaforth Dock, Seaforthrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 2.8 |
| Litherland High School, Sterrix Lanerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Sefton | 2.9 |
| Merlin AFS, Royal Seaforth Dockrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 2.9 |
| Peel Road Energy Centrebattery storage | battery storage | — | permission expiredupdated Apr 2020 | Sep 2017 | granted Jun 2018 | Apr 2020 | Sefton | 3.8 |
| Pawfect Retreat, Moor Farmrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Sefton | 3.8 |
| Cwt Maintenance Building, Regent Roadrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 3.9 |
| Heysham Box, Leckwith Roadbattery storage | battery storage | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | Sefton | 4.4 |
| Heysham Box, Leckwith Roadbattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Sefton | 4.4 |
| Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 4.5 |
| Multiuser 2 Building, Regent Roadrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 4.6 |
| Royal Seaforth Dock, New Jenkins Shedsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 4.8 |
| Multiuser 4 Buildingrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 4.8 |
| Multiuser 1 Building, Regent Roadrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Sefton | 4.8 |
| SCS Lighting & Renewables, Aintreerooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Jun 2022 | Jun 2022 | — | Jun 2022 | Sefton | 5.0 |
| Multiuser 5 Building, Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Sefton | 5.1 |
| Meadows Leisure Centre, Hall Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | Sefton | 5.4 |
| Temp Control Buildingrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Sefton | 5.7 |
| Deyes Academy Redevelopmentrooftop solar | rooftop solar | 0.6 | under constructionupdated Aug 2022 | Mar 2022 | granted Jun 2022 | Aug 2022 | Sefton | 6.0 |
| Waste Care, Lower Bank Viewrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Dec 2024 | granted Feb 2025 | Mar 2025 | Liverpool | 6.1 |
| Bulk Powder Terminals, Regent Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Liverpool | 6.4 |
| Steel Terminal, Royal Seaforth Dockrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Liverpool | 6.5 |
| Suttons Farm, Lord Sefton Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2024 | Apr 2024 | granted Jun 2024 | Jun 2024 | West Lancashire | 6.8 |
| Jeffrey Humble Playing Fields, Long Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Liverpool | 7.2 |
| Rowan View Hospital, Villas Roadrooftop solar | rooftop solar | — | approved, not builtupdated May 2026 | Nov 2025 | granted Apr 2026 | May 2026 | Sefton | 7.9 |
| Rowan View Hospital, Villas Roadbattery storage | battery storage | — | approved, not builtupdated May 2026 | Nov 2025 | granted Apr 2026 | May 2026 | Sefton | 7.9 |
| St Marys College, Wallasey Villagerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Wirral | 8.0 |
| Sainsburys, Jennifer Avenuerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Aug 2023 | Jul 2023 | granted Aug 2023 | Aug 2023 | Liverpool | 8.1 |
| Formby High Schoolrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | Sefton | 8.3 |
| North Liverpool Academy, Heyworth Streetrooftop solar | rooftop solar | 0.2 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Liverpool | 8.3 |
| Mercedes-Benz, Pall Mallrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Aug 2022 | Jul 2022 | Liverpool | 8.9 |
| Dixons Croxteth Academy, Carr Lane Eastrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | Liverpool | 9.1 |
| Tesco, Bidston Link Road, Bidstonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Wirral | 9.8 |
| Tesco Pharmacy, Bidstonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Feb 2026 | granted May 2026 | Jun 2026 | Wirral | 9.8 |
| Port Of Liverpool Building, Mann Islandrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Dec 2025 | granted Feb 2026 | Jan 2026 | Liverpool | 9.9 |
| Valley Road, Bidstonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Wirral | 9.9 |
Distance from the average position of the L23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 3 | 0 | 2 | 19 |
| Rooftop solar | 41 | 4 | 37 | 0 | 0 | 10.7 |
| Wind farm | 3 | 0 | 0 | 2 | 1 | 0 |
| Battery storage | 9 | 0 | 5 | 1 | 0 | 20.6 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 10.7 |
| Burbo Bank Extension (Burbo Bank 2) | 258 | operationalupdated May 2018 | 16.4 |
| North Hoyle | 60 | operationalupdated Aug 2017 | 29.4 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Sefton decides solar, wind and battery applications
| Applications | Sefton | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 4 (10%) | 19% |
| Solar refused | 3 of 33 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 7.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near L23, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.