Hawthorne Road (20 MW battery storage)

Hawthorne Road is a 20 MW battery storage project in Sefton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 30 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
under constructionstatus in REPD
30 September 2020record last updated
Seftoncouncil area

Planning timeline

DateStage
29 January 2020Application submitted
29 March 2022Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
under construction
Record last updated
30 September 2020
Operator or applicant
Bluefield Renewable Developments
Planning authority
Sefton
Planning application reference
DC/2020/00085
Address (REPD)
491 Linacre Lane, Bootle, Merseyside
Council area (by location)
Sefton
Time to decision
113 weeks
REPD reference
7800

Who decides

ApplicationsSeftonUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused3 of 3312%
Onshore wind refused0 of 245%
Battery storage refused1 of 516%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Port of Liverpool windwind farm10operational1.6
Land at Carnegie Roadbattery storage20operational5.9
Carnegie Road (Phase 2)battery storage40permission expired5.9
Lister Drivebattery storage49.9operational5.9
Liverpool Energy Management Facilitybattery storage49.9operational5.9
Battery Energy Storage Systembattery storage6approved, not built6.5
Britannia Housebattery storage10permission expired7.0
Beaufort Roadbattery storage20permission expired7.5
Lower Alt Wind Farmwind farm42refused8.2