Energy Projects Near You

Solar, wind and battery projects near Liverpool (L4)

81 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L4 (Liverpool): 10 are waiting for a planning decision, 57 approved but not yet running, 7 operational. The largest live scheme is Perimeter Road, Kirkby (165 MW battery storage, application submitted on 14 November 2025, no decision recorded), 9.0 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 15.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

81projects within 10 km
10awaiting a decision
57approved, not running
7operational

Projects within 10 km of L4

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hawthorne Roadbattery storagebattery storage20under constructionupdated Sep 2020Jan 2020granted Mar 2022Sep 2020Sefton2.9
Land at Carnegie Roadbattery storagebattery storage20operationalupdated Jan 2019Nov 2016—Jan 2019Liverpool3.0
Lister Drivebattery storagebattery storage49.9operationalupdated Jan 2023Feb 2020granted Mar 2021Jan 2023Liverpool3.0
Liverpool Energy Management Facilitybattery storagebattery storage49.9operationalupdated Mar 2022Feb 2020granted Nov 2020Mar 2022Liverpool3.0
Carnegie Road (Phase 2)battery storagebattery storage40permission expiredupdated Jun 2019Mar 2019granted Dec 2019Jun 2019Liverpool3.0
Huskisson Dock Building, Huskisson Dockrooftop solarrooftop solar1.5approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Liverpool3.1
Port of Liverpool windwind farmwind farm10operationalupdated Jun 2010Aug 2005granted Dec 2005Jun 2010Sefton3.2
Battery Energy Storage Systembattery storagebattery storage6approved, not builtupdated May 2025Nov 2024granted Apr 2025May 2025Liverpool3.6
Royal Seaforth Dock, New Jenkins Shedsrooftop solarrooftop solar2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton5.1
D H L Exel Supply Chain Burton Foods, Portal Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Liverpool5.3
Royal Seaforth Dock Wind Farmwind farmwind farm3operationalupdated Feb 2003Oct 1995granted Aug 1997Feb 2003Sefton6.0
Larkins Farm, Gellings Lane Solar Farmsolar farmsolar farm1.5refusedupdated Aug 2024Oct 2023refused Jul 2024Aug 2024Knowsley6.4
Britannia Housebattery storagebattery storage10permission expiredupdated Oct 2023Sep 2017granted Dec 2017Oct 2023Wirral6.7
Burbo Bank Energy Storagebattery storagebattery storage2operationalupdated Feb 2020Apr 2017—Feb 2020Wirral6.8
Beaufort Roadbattery storagebattery storage20permission expiredupdated Apr 2020Sep 2016—Apr 2020Wirral7.0
Coopers Lane, Kirkbybattery storagebattery storage49.5approved, not builtupdated May 2024Jul 2023granted Apr 2024May 2024Knowsley8.1
Charleywood Road, Knowsley Industrial Parkbattery storagebattery storage49.9abandonedupdated Sep 2022Oct 2017—Sep 2022Knowsley8.2
Perimeter Road, Kirkbybattery storagebattery storage165application submittedupdated Dec 2025Nov 2025—Dec 2025Knowsley9.0
Cut Lanebattery storagebattery storage57application submittedupdated Jun 2025Apr 2025—Jun 2025Knowsley9.1
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
North Liverpool Academy, Heyworth Streetrooftop solarrooftop solar0.2application submittedupdated Aug 2025Jul 2025—Aug 2025Liverpool1.6
Sainsburys, Jennifer Avenuerooftop solarrooftop solar0.5approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Liverpool2.0
Waste Care, Lower Bank Viewrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Liverpool2.4
Steel Terminal, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Liverpool2.4
Jeffrey Humble Playing Fields, Long Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Liverpool2.6
Bulk Powder Terminals, Regent Roadrooftop solarrooftop solar0.7approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Liverpool2.6
Multiuser 5 Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton2.8
Royal Seaforth Dock, New Jenkins Shedsrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.1
Multiuser 4 Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.1
Multiuser 1 Building, Regent Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.1
Temp Control Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton3.2
Multiuser 2 Building, Regent Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.4
Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.4
Stanley Meat Market, Prescot Road Solar PV Systemsrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Jul 2024Sep 2024Liverpool3.4
Mercedes-Benz, Pall Mallrooftop solarrooftop solar0.3approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022Liverpool3.4
Dixons Croxteth Academy, Carr Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Liverpool3.8
Cwt Maintenance Building, Regent Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.9
The Big Yellow Self Storage, Mill Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Liverpool4.3
Port Of Liverpool Building, Mann Islandrooftop solarrooftop solar—approved, not builtupdated Jan 2026Dec 2025granted Feb 2026Jan 2026Liverpool4.3
SCS Lighting & Renewables, Aintreerooftop solarrooftop solar0.3application submitted may be out of dateupdated Jun 2022Jun 2022—Jun 2022Sefton4.6
Alder Hey Hospital, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Jan 2026granted Mar 2026Jun 2026Liverpool4.6
Peel Road Energy Centrebattery storagebattery storage—permission expiredupdated Apr 2020Sep 2017granted Jun 2018Apr 2020Sefton4.7
Sainsburys Supermarket, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Liverpool4.9
Litherland High School, Sterrix Lanerooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sefton4.9
Heysham Box, Leckwith Roadbattery storagebattery storage0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Sefton5.1
Heysham Box, Leckwith Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Sefton5.1
Royal Seaforth Dock, CWT Stores Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton5.1
Maritime Stores, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton5.1
Rubies 1 Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton5.1
Rubies 2 Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton5.1
Briggs Marine, Langton Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton5.1
Maritime IT Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton5.1
Rubies 3 Building, Royal Seaforth Dockrooftop solarrooftop solar—application submitted may be out of dateupdated Jan 2024Jan 2024—Jan 2024Sefton5.3
Royal Seaforth Dock, Seaforthrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton5.3
Merlin AFS, Royal Seaforth Dockrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton5.4
CWT North Building, Royal Seaforth Dockrooftop solarrooftop solar0.1approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton5.5
Tipographic, Morpeth Wharfrooftop solarrooftop solar0.8approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Wirral5.6
HMS Eaglet, Sefton Street Wind Turbine & Solar Panelsrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Liverpool5.8
HMS Eaglet, Sefton Street Wind Turbine & Solar Panelswind turbinewind turbine—application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Liverpool5.8
Tesco Superstorerooftop solarrooftop solar—approved, not builtupdated Mar 2021Jan 2021granted Apr 2021Mar 2021Liverpool5.9
Aigburth Parkrooftop solarrooftop solar—approved, not builtupdated Apr 2021Feb 2021granted May 2021Apr 2021Liverpool7.0
Peter Gilding And Company, Caddick Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2024Oct 2024granted Dec 2024Dec 2024Knowsley7.0
St Marys College, Wallasey Villagerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Wirral7.0
Adlib House, Kitling Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Knowsley7.1
Penrhyn Court, Penrhyn Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Jan 2026granted Feb 2026May 2026Knowsley7.1
Beverston Engineering, Unit Brooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Knowsley7.1
Knowsley Industrial Parkrooftop solarrooftop solar0.3approved, not builtupdated Apr 2022Nov 2020granted Jan 2021Apr 2022Knowsley7.6
Leisure United Jericho Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Liverpool7.8
Valley Road, Bidstonrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Wirral7.8
Meadows Leisure Centre, Hall Lanerooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Sefton7.8
Tesco, Bidston Link Road, Bidstonrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Wirral7.9
Tesco Pharmacy, Bidstonrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Feb 2026granted May 2026Jun 2026Wirral7.9
David Lloyd Leisure, Arbour Lanerooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Knowsley8.0
Henry Diaper, Knowsley Industrial Parkrooftop solarrooftop solar0.2application submitted may be out of dateupdated May 2023May 2023—May 2023Knowsley8.0
Charley Wood Road, Knowsley Industrial Park Solar Photovoltaicsrooftop solarrooftop solar0.9approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023Knowsley8.2
Deyes Academy Redevelopmentrooftop solarrooftop solar0.6under constructionupdated Aug 2022Mar 2022granted Jun 2022Aug 2022Sefton8.4
Earlsfield Park, Arley Driverooftop solarrooftop solar0.1application submittedupdated Feb 2025Jan 2025—Feb 2025Knowsley9.0
Sainsburys, Woodchurch Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Wirral9.0
IBL Cold Stores Solar Photovoltaics Panelsrooftop solarrooftop solar0.8operationalupdated Oct 2021Oct 2021granted Feb 2022Oct 2021Knowsley9.3
Moss End Way, Kirkby Knowsleybattery storagebattery storage0.2refusedupdated Jun 2026Dec 2025refused Apr 2026Jun 2026Knowsley9.4

2 more projects not listed (furthest or smallest).

Distance from the average position of the L4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100010
Rooftop solar577491014.8
Wind farm200200
Wind turbine110000
Battery storage202841298

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201815.8
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201821.0
North Hoyle60operationalupdated Aug 201732.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Liverpool decides solar, wind and battery applications

ApplicationsLiverpoolUK
Decided applications (solar, wind, battery)2610,236
Refused0 (0%)19%
Solar refused0 of 1812%
Battery storage refused0 of 816%
Median time from submission to decision7.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Liverpool

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near L4, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.