Lister Drive (49.9 MW battery storage)

Lister Drive is a 49.9 MW battery storage project in Liverpool, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational; the record was last updated on 4 January 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
4 January 2023record last updated
Liverpoolcouncil area

Planning timeline

DateStage
4 February 2020Application submitted
2 March 2021Planning permission granted
1 May 2021Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
4 January 2023
Operator or applicant
Arenko Cleantech / Stratcraft
Planning authority
Liverpool
Planning application reference
20F/0335
Address (REPD)
Land Adjacent to Lister Drive, Carnegie Road, Liverpool,
Council area (by location)
Liverpool
Time to decision
56 weeks
REPD reference
7740

Who decides

ApplicationsLiverpoolUK
Decided applications (solar, wind, battery)2610,236
Refused0 (0%)19%
Solar refused0 of 1812%
Battery storage refused0 of 816%
Median time from submission to decision7.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Liverpool Energy Management Facilitybattery storage49.9operational<0.1
Carnegie Road (Phase 2)battery storage40permission expired<0.1
Land at Carnegie Roadbattery storage20operational<0.1
Battery Energy Storage Systembattery storage6approved, not built0.6
Hawthorne Roadbattery storage20under construction5.9
Port of Liverpool windwind farm10operational6.1
Coopers Lane, Kirkbybattery storage49.5approved, not built7.4
Charleywood Road, Knowsley Industrial Parkbattery storage49.9abandoned7.9
Britannia Housebattery storage10permission expired8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4199, -2.9276).