Charleywood Road, Knowsley Industrial Park (49.9 MW battery storage)

Charleywood Road, Knowsley Industrial Park is a 49.9 MW battery storage project in Knowsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 14 September 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
abandonedstatus in REPD
14 September 2022record last updated
Knowsleycouncil area

Planning timeline

DateStage
26 October 2017Application submitted
21 December 2020Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
abandoned
Record last updated
14 September 2022
Operator or applicant
Immersa / Kirkby Battery Storage 2
Planning authority
Knowsley
Planning application reference
17/00649/FUL
Address (REPD)
Land At Eldapoint, Charleywood Road, Knowsley Industrial Park, Liverpool, Merseyside
Council area (by location)
Knowsley
REPD reference
7026

Who decides

ApplicationsKnowsleyUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused4 of 1812%
Battery storage refused1 of 216%
Median time from submission to decision7.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Knowsley, Knowsley Borough.

Other large projects within 10 km

ProjectTypeMWStatuskm
Perimeter Road, Kirkbybattery storage165application submitted0.8
Coopers Lane, Kirkbybattery storage49.5approved, not built1.2
Cut Lanebattery storage57application submitted1.8
Gerard Hall Solar Farmsolar farm17refused on appeal6.2
Carnegie Road (Phase 2)battery storage40permission expired7.9
Lister Drivebattery storage49.9operational7.9
Liverpool Energy Management Facilitybattery storage49.9operational7.9
Land at Carnegie Roadbattery storage20operational7.9
Battery Energy Storage Systembattery storage6approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4779, -2.8578).