Cut Lane (57 MW battery storage)

Cut Lane is a 57 MW battery storage project in Knowsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 April 2025, no decision recorded; the record was last updated on 27 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
application submittedstatus in REPD
27 June 2025record last updated
Knowsleycouncil area

Planning timeline

DateStage
2 April 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
application submitted
Record last updated
27 June 2025
Operator or applicant
Pivoted Power Llp
Planning authority
Knowsley
Planning application reference
25/00228/FUL
Address (REPD)
N/O Cut Lane, Liverpool
Council area (by location)
Knowsley
Name in REPD
Cut Lane - Battery Energy Storage System
REPD reference
16131

Who decides

ApplicationsKnowsleyUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused4 of 1812%
Battery storage refused1 of 216%
Median time from submission to decision7.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Knowsley, Knowsley Borough.

Other large projects within 10 km

ProjectTypeMWStatuskm
Coopers Lane, Kirkbybattery storage49.5approved, not built1.0
Perimeter Road, Kirkbybattery storage165application submitted1.7
Charleywood Road, Knowsley Industrial Parkbattery storage49.9abandoned1.8
Burtonhead Roadbattery storage30abandoned7.1
Gerard Hall Solar Farmsolar farm17refused on appeal7.8
Battery Energy Storage Systembattery storage6approved, not built8.2
Lister Drivebattery storage49.9operational8.3
Carnegie Road (Phase 2)battery storage40permission expired8.3
Liverpool Energy Management Facilitybattery storage49.9operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4698, -2.8349).