Solar, wind and battery projects near St Helens (WA10)
60 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WA10 (St. Helens): 9 are waiting for a planning decision, 37 approved but not yet running, 3 operational. The largest live scheme is Perimeter Road, Kirkby (165 MW battery storage, application submitted on 14 November 2025, no decision recorded), 6.8 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 28.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WA10
Projects of 1 MW and more (27)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Biffa Electricity Generating Compound, Burtonhead Roadbattery storage | battery storage | 1 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | St. Helens | 1.4 |
| College Streetrooftop solar | rooftop solar | 1.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | St. Helens | 1.5 |
| Burtonhead Roadbattery storage | battery storage | 30 | abandonedupdated Feb 2019 | Oct 2017 | — | Feb 2019 | St. Helens | 1.7 |
| Sutton Manorbattery storage | battery storage | 57 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Sep 2022 | Jun 2022 | St. Helens | 4.0 |
| Cut Lanebattery storage | battery storage | 57 | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | Knowsley | 5.5 |
| Holiday Moss Landfill Site, Reeds Browbattery storage | battery storage | 3 | approved, not built may be out of dateupdated Dec 2022 | Sep 2022 | granted Nov 2022 | Dec 2022 | St. Helens | 5.9 |
| Coopers Lane, Kirkbybattery storage | battery storage | 49.5 | approved, not builtupdated May 2024 | Jul 2023 | granted Apr 2024 | May 2024 | Knowsley | 6.4 |
| Promised Land Farmwind farm | wind farm | 1 | operationalupdated Feb 2017 | May 2013 | granted Oct 2013 | Feb 2017 | St. Helens | 6.5 |
| Perimeter Road, Kirkbybattery storage | battery storage | 165 | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Knowsley | 6.8 |
| Charleywood Road, Knowsley Industrial Parkbattery storage | battery storage | 49.9 | abandonedupdated Sep 2022 | Oct 2017 | — | Sep 2022 | Knowsley | 7.2 |
| Land South Of Joy Lanesolar farm | solar farm | 5 | refusedupdated Sep 2015 | May 2015 | refused Aug 2015 | Sep 2015 | Warrington | 7.7 |
| Lockheed Road, Burtonwood & Westbrookrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Warrington | 7.7 |
| Larkins Farm, Gellings Lane Solar Farmsolar farm | solar farm | 1.5 | refusedupdated Aug 2024 | Oct 2023 | refused Jul 2024 | Aug 2024 | Knowsley | 7.8 |
| Mill Farmsolar farm | solar farm | 5 | abandonedupdated Dec 2018 | Jul 2015 | granted Dec 2015 | Dec 2018 | Wigan | 7.9 |
| The Hut Group, Skyline Driverooftop solar | rooftop solar | 6.8 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Warrington | 8.0 |
| The Hut Group, Skyline Driverooftop solar | rooftop solar | 1.5 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Warrington | 8.0 |
| Sandyforth Farm, Ashton Roadbattery storage | battery storage | 70 | approved, not builtupdated Apr 2025 | Feb 2024 | granted Feb 2025 | Apr 2025 | Wigan | 8.0 |
| Barton House Farm, Pimbo Roadwind turbine | wind turbine | 2.5 | approved, not builtupdated Jun 2026 | Jan 2025 | granted Apr 2026 | Jun 2026 | West Lancashire | 8.2 |
| Amazon Omega Business Parkrooftop solar | rooftop solar | 1.5 | operationalupdated Jan 2020 | Feb 2019 | granted Apr 2019 | Jan 2020 | Warrington | 8.3 |
| Fairchild Road, Burtonwood & Westbrookrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Oct 2023 | Nov 2023 | Warrington | 8.4 |
| Far Moorbattery storage | battery storage | 50 | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | West Lancashire | 8.5 |
| Pikelaw Placebattery storage | battery storage | 10 | permission expiredupdated Aug 2020 | May 2017 | granted Jul 2017 | Aug 2020 | West Lancashire | 8.9 |
| D H L Exel Supply Chain Burton Foods, Portal Wayrooftop solar | rooftop solar | 1 | application submitted may be out of dateupdated Jul 2023 | Jun 2023 | — | Jul 2023 | Liverpool | 9.3 |
| Tontine Roadbattery storage | battery storage | 70 | application submitted may be out of dateupdated Oct 2021 | Jan 2023 | — | Oct 2021 | West Lancashire | 9.4 |
| Causeway Bridges Wind Farmwind farm | wind farm | 4 | abandonedupdated Jul 2014 | Apr 2008 | granted May 2008 | Jul 2014 | Warrington | 9.5 |
| Mowcroft Solar Farmsolar farm | solar farm | 27.1 | refusedupdated Dec 2025 | Jul 2025 | refused Oct 2025 | Dec 2025 | Warrington | 9.6 |
| Poundland Distribution Centre,Three Sisters Roadrooftop solar | rooftop solar | 2.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Wigan | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (33)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Queens Park Health And Fitnessrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | St. Helens | 0.4 |
| Arnold Clark Renault, Delphwood Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | St. Helens | 2.2 |
| St Helens Rugby League Stadium, Peasley Cross Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2023 | Nov 2022 | granted Jan 2023 | Mar 2023 | St. Helens | 2.4 |
| DTC St Helens Hospital, Marshalls Cross Roadrooftop solar | rooftop solar | 0.2 | refusedupdated May 2024 | Mar 2024 | refused May 2024 | May 2024 | St. Helens | 2.9 |
| Mere Grange, Leasiderooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted Jun 2025 | Jun 2025 | St. Helens | 3.1 |
| The Sutton Academy, Elton Head Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | St. Helens | 3.5 |
| Lea Green Business Park, Eurolinkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | St. Helens | 4.1 |
| Lea Green Business Park, Eurolinkrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | St. Helens | 4.1 |
| Whiston Hospital, Warrington Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Oct 2025 | granted Dec 2025 | Apr 2026 | Knowsley | 4.2 |
| Earlsfield Park, Arley Driverooftop solar | rooftop solar | 0.1 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Knowsley | 5.5 |
| Bellerophon Way Tescorooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Sep 2020 | Mar 2019 | granted May 2019 | Sep 2020 | St. Helens | 6.1 |
| Peter Gilding And Company, Caddick Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Dec 2024 | Dec 2024 | Knowsley | 7.0 |
| Adlib House, Kitling Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Sep 2023 | Oct 2023 | Knowsley | 7.0 |
| Enviropax, Hall Wood Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | St. Helens | 7.0 |
| IBL Cold Stores Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.8 | operationalupdated Oct 2021 | Oct 2021 | granted Feb 2022 | Oct 2021 | Knowsley | 7.0 |
| Moss End Way, Kirkby Knowsleybattery storage | battery storage | 0.2 | refusedupdated Jun 2026 | Dec 2025 | refused Apr 2026 | Jun 2026 | Knowsley | 7.0 |
| Penrhyn Court, Penrhyn Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Jan 2026 | granted Feb 2026 | May 2026 | Knowsley | 7.1 |
| Beverston Engineering, Unit Brooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Knowsley | 7.1 |
| Charley Wood Road, Knowsley Industrial Park Solar Photovoltaicsrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | Knowsley | 7.2 |
| Knowsley Industrial Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2022 | Nov 2020 | granted Jan 2021 | Apr 2022 | Knowsley | 7.2 |
| Starbank Panel Products, Junction Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | St. Helens | 7.5 |
| Omega West, St Helens, Unit 4, Zone 8rooftop solar | rooftop solar | 0.7 | application withdrawnupdated Feb 2025 | Nov 2024 | — | Feb 2025 | St. Helens | 7.6 |
| Henry Diaper, Knowsley Industrial Parkrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated May 2023 | May 2023 | — | May 2023 | Knowsley | 7.6 |
| City Plumbing, Lockheed Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Warrington | 7.7 |
| Rivendell Nurseriesrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Halton | 7.8 |
| David Lloyd Leisure, Arbour Lanerooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Knowsley | 7.9 |
| Dominos Pizza, Skyline Driverooftop solar | rooftop solar | 1 | approved, not builtupdated Feb 2023 | Jan 2023 | granted Feb 2023 | Feb 2023 | Warrington | 8.1 |
| Haweswater Car Park Solar Canopysolar farm | solar farm | 0.9 | approved, not builtupdated Oct 2024 | May 2024 | granted Oct 2024 | Oct 2024 | Warrington | 8.2 |
| Pimbo Road, By Paxton Place Jnct - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | application submitted | Apr 2026 | — | — | West Lancashire | 8.3 |
| Stopgate Lane, Simonswoodrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | West Lancashire | 8.4 |
| Newton Le Willows Health And Fitnessrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | St. Helens | 8.7 |
| St Francis Of Assisi Catholic Primary Schoolrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | West Lancashire | 9.7 |
| Arnold Clark Automobiles, Europa Boulevardrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2024 | May 2025 | Warrington | 9.8 |
Distance from the average position of the WA10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 0 | 1 | 0 | 3 | 0.9 |
| Rooftop solar | 38 | 4 | 30 | 2 | 1 | 25.1 |
| Wind farm | 2 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 2.5 |
| Battery storage | 14 | 5 | 5 | 0 | 1 | 523 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 28.6 |
| Burbo Bank Extension (Burbo Bank 2) | 258 | operationalupdated May 2018 | 34.1 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How St. Helens decides solar, wind and battery applications
| Applications | St. Helens | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 1 of 13 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 7.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WA10, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.