Energy Projects Near You

Sutton Manor (57 MW battery storage)

Sutton Manor is a 57 MW battery storage project in St. Helens, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 September 2022, not yet built; the record was last updated on 28 June 2022. REPD also records that the planning permission expired on 16 September 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
approved, not builtmay be out of datestatus in REPD
28 June 2022record last updated
St. Helenscouncil area

REPD also records that the planning permission expired on 16 September 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
6 June 2022Application submitted
16 September 2022Planning permission granted
16 September 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
approved, not built
Record last updated
28 June 2022
Operator or applicant
Sizing John Limited
Planning authority
St. Helens
Planning application reference
P/2022/0392/FUL
Address (REPD)
S/O National Grid's Rainhill Substation Lea Green Road Sutton Manor St Helens
Council area (by location)
St. Helens
Time to decision
15 weeks
Name in REPD
Sutton Manor - Battery Storage Facility
REPD reference
11559

Earlier applications for this site

ApplicationMWSubmittedOutcome
National Grids Rainhill Substation Battery storage facility P/2021/0094/FUL572 February 2021replaced by a revised application

Who decides

ApplicationsSt. HelensUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused1 of 1312%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision7.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burtonhead Roadbattery storage30abandoned2.6
The Hut Group, Skyline Driverooftop solar6.8approved, not built5.3
Land South Of Joy Lanesolar farm5refused5.3
Mowcroft Solar Farmsolar farm27.1refused5.7
Fiddlers Ferry Power Stationbattery storage150under construction6.2
St Michaels Road, Ditton Roadbattery storage14approved, not built7.0
Station Road, Fiddlers Ferrybattery storage250refused7.3
Land south of 50 Station Roadsolar farm5refused7.3
Cut Lanebattery storage57application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4197, -2.7385).