Station Road, Fiddlers Ferry (250 MW battery storage)

Station Road, Fiddlers Ferry is a 250 MW battery storage project in Warrington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 December 2025; the record was last updated on 16 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

250 MWbattery storage
refusedstatus in REPD
16 December 2025record last updated
Warringtoncouncil area

Planning timeline

DateStage
18 July 2025Application submitted
4 December 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
250 MW
Status (REPD)
refused
Record last updated
16 December 2025
Operator or applicant
Net Zero One Limited
Planning authority
Warrington
Planning application reference
2025/00999/FULM
Address (REPD)
South West Of Station Road, Fiddlers Ferry, Penketh
Council area (by location)
Warrington
Time to decision
20 weeks
Name in REPD
Station Road, Fiddlers Ferry - Battery Energy Storage
REPD reference
18975

Who decides

ApplicationsWarringtonUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused5 of 3012%
Onshore wind refused0 of 145%
Battery storage refused1 of 416%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land south of 50 Station Roadsolar farm5refused1.0
Fiddlers Ferry Power Stationbattery storage150under construction1.8
Mowcroft Solar Farmsolar farm27.1refused2.0
Warrington Home Solar Schemerooftop solar5.3operational4.2
The Hut Group, Skyline Driverooftop solar6.8approved, not built4.3
Land South Of Joy Lanesolar farm5refused4.8
St Michaels Road, Ditton Roadbattery storage14approved, not built6.9
Sutton Manorbattery storage57approved, not built7.3
Cholmondeley Roadbattery storage150approved, not built7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3732, -2.6614).