Energy Projects Near You

Solar, wind and battery projects near Warrington (WA5)

61 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WA5 (Warrington): 1 is waiting for a planning decision, 42 approved but not yet running, 4 operational. The largest live scheme is Fiddlers Ferry Power Station (150 MW battery storage, under construction since 28 March 2024), 4.4 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 37.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

61projects within 10 km
1awaiting a decision
42approved, not running
4operational

Projects within 10 km of WA5

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Amazon Omega Business Parkrooftop solarrooftop solar1.5operationalupdated Jan 2020Feb 2019granted Apr 2019Jan 2020Warrington1.6
Fairchild Road, Burtonwood & Westbrookrooftop solarrooftop solar1approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Warrington1.6
The Hut Group, Skyline Driverooftop solarrooftop solar6.8approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Warrington1.9
The Hut Group, Skyline Driverooftop solarrooftop solar1.5approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Warrington1.9
Land South Of Joy Lanesolar farmsolar farm5refusedupdated Sep 2015May 2015refused Aug 2015Sep 2015Warrington2.3
Lockheed Road, Burtonwood & Westbrookrooftop solarrooftop solar1.8approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Warrington2.3
Land south of 50 Station Roadsolar farmsolar farm5refusedupdated Sep 2015May 2015refused Aug 2015Sep 2015Warrington2.3
Warrington Home Solar Schemerooftop solarrooftop solar5.3operationalupdated Jul 2016——Jul 2016Warrington2.8
Causeway Bridges Wind Farmwind farmwind farm4abandonedupdated Jul 2014Apr 2008granted May 2008Jul 2014Warrington3.0
Station Road, Fiddlers Ferrybattery storagebattery storage250refusedupdated Dec 2025Jul 2025refused Dec 2025Dec 2025Warrington3.3
Mowcroft Solar Farmsolar farmsolar farm27.1refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025Warrington4.1
Fiddlers Ferry Power Stationbattery storagebattery storage150under constructionupdated Mar 2024Jul 2022granted Jun 2023Mar 2024Warrington4.4
Former St Michaels Golf Coursesolar farmsolar farm1under constructionupdated Oct 2018Feb 2018granted Apr 2018Oct 2018Warrington4.9
Johnson's Lane - Warringtonsolar farmsolar farm1.5abandonedupdated Jun 2019Jun 2015granted Feb 2016Jun 2019Halton5.1
Johnson's Lane - Haltonsolar farmsolar farm3.5abandonedupdated Jun 2019Jun 2015granted Oct 2015Jun 2019Halton5.4
Sutton Manorbattery storagebattery storage57approved, not built may be out of dateupdated Jun 2022Jun 2022granted Sep 2022Jun 2022St. Helens7.0
Clares Farm Closewind farmwind farm2.6application withdrawnupdated May 2009——May 2009Warrington8.0
Burtonhead Roadbattery storagebattery storage30abandonedupdated Feb 2019Oct 2017—Feb 2019St. Helens8.1
Biffa Electricity Generating Compound, Burtonhead Roadbattery storagebattery storage1approved, not built may be out of dateupdated Nov 2022Aug 2022granted Oct 2022Nov 2022St. Helens8.5
Kenyon Lanesolar farmsolar farm5refusedupdated Jan 2016Sep 2015refused Dec 2015Jan 2016Warrington8.7
Hedco, Desoto Roadsolar farmsolar farm3.5approved, not builtupdated May 2026May 2022granted Jun 2024May 2026Halton8.8
College Streetrooftop solarrooftop solar1.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024St. Helens9.3
St Michaels Road, Ditton Roadbattery storagebattery storage14approved, not builtupdated Nov 2023Nov 2022granted Oct 2023Nov 2023Halton9.3
Ditton Road Solar Microgridsolar farmsolar farm4approved, not builtupdated Feb 2026Jun 2024granted Jan 2025Feb 2026Halton9.5
Smaller schemes under 1 MW, mostly rooftop solar (37)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dominos Pizza, Skyline Driverooftop solarrooftop solar1approved, not builtupdated Feb 2023Jan 2023granted Feb 2023Feb 2023Warrington1.9
Haweswater Car Park Solar Canopysolar farmsolar farm0.9approved, not builtupdated Oct 2024May 2024granted Oct 2024Oct 2024Warrington1.9
Warrington Teaching Hospital, Lovely Lanerooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Warrington2.0
Arnold Clark Automobiles, Europa Boulevardrooftop solarrooftop solar0.2approved, not builtupdated May 2025Mar 2025granted Apr 2024May 2025Warrington2.2
City Plumbing, Lockheed Roadrooftop solarrooftop solar0.6approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Warrington2.3
Omega West, St Helens, Unit 4, Zone 8rooftop solarrooftop solar0.7application withdrawnupdated Feb 2025Nov 2024—Feb 2025St. Helens2.5
Halliwell Jones Stadium, Winwick Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Warrington3.0
Christeyns Food Hygiene, Cameron Courtrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Warrington3.4
Units 2-4 Opus 9 Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Apr 2022Mar 2022granted May 2022Apr 2022Warrington3.5
Beamont Collegiate Academy, Long Lanerooftop solarrooftop solar0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Warrington3.5
Morrisons, Greenalls Avenuerooftop solarrooftop solar0.5refusedupdated May 2025Feb 2025refused Apr 2025May 2025Warrington4.6
Rivendell Nurseriesrooftop solarrooftop solar0.2application submittedJun 2026——Halton5.2
Starbank Panel Products, Junction Lanerooftop solarrooftop solar0.5approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022St. Helens5.4
Pembroke Court, Haltonrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Halton5.6
Sutton International, Gorsey Lane Solar PV Arraysrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Halton5.9
Grappenhall Village Sports Club, Stockton Lanebattery storagebattery storage0.2approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Warrington5.9
Daresbury Science Parksolar farmsolar farm0.6operationalupdated Jan 2022Aug 2021granted Jan 2022Jan 2022Halton6.0
Newton Le Willows Health And Fitnessrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025St. Helens6.8
The Sutton Academy, Elton Head Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025St. Helens6.8
DTC St Helens Hospital, Marshalls Cross Roadrooftop solarrooftop solar0.2refusedupdated May 2024Mar 2024refused May 2024May 2024St. Helens7.0
Britplas Commercial Windows, Kingsland Grangerooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Warrington7.0
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.6approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024St. Helens7.1
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025St. Helens7.2
Warrington Vehicle Centre, Hardwick Grangerooftop solarrooftop solar0.7approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Warrington7.5
Mere Grange, Leasiderooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025St. Helens7.5
Bellerophon Way Tescorooftop solarrooftop solar0.4approved, not built may be out of dateupdated Sep 2020Mar 2019granted May 2019Sep 2020St. Helens7.5
Arnold Clark Renault, Delphwood Driverooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026St. Helens7.6
St Helens Rugby League Stadium, Peasley Cross Lanerooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Nov 2022granted Jan 2023Mar 2023St. Helens7.7
Genesis Centre, Garrett Fieldrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Warrington7.9
Spire Cheshire Hospital, Fir Tree Close Solar PV Systemsrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Warrington8.0
Mercedes Benz, Juniper Lanerooftop solarrooftop solar0.2approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022Warrington8.5
Enviropax, Hall Wood Avenuerooftop solarrooftop solar0.2approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026St. Helens8.6
Sortimo, Appleton Thornrooftop solarrooftop solar0.3application withdrawnupdated May 2026Feb 2026—May 2026Warrington8.8
Leiria Way Car Parkbattery storagebattery storage—operationalupdated Feb 2021Feb 2020granted May 2020Feb 2021Halton8.8
Queens Park Health And Fitnessrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025St. Helens9.6
Phoenix Medical Supplies, Rivington Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Dec 2022granted Feb 2023Mar 2023Halton9.9
Whiston Hospital, Warrington Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Oct 2025granted Dec 2025Apr 2026Knowsley9.9

Distance from the average position of the WA5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1104149.4
Rooftop solar401332222.1
Wind farm200000
Battery storage80511222

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201837.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Warrington decides solar, wind and battery applications

ApplicationsWarringtonUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused5 of 3012%
Onshore wind refused0 of 145%
Battery storage refused1 of 416%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Warrington

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WA5, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.