Solar, wind and battery projects near St Helens (WA9)
60 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WA9 (St. Helens): 4 are waiting for a planning decision, 42 approved but not yet running, 3 operational. The largest live scheme is Perimeter Road, Kirkby (165 MW battery storage, application submitted on 14 November 2025, no decision recorded), 10.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 31.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WA9
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Burtonhead Roadbattery storage | battery storage | 30 | abandonedupdated Feb 2019 | Oct 2017 | — | Feb 2019 | St. Helens | 1.4 |
| Biffa Electricity Generating Compound, Burtonhead Roadbattery storage | battery storage | 1 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | St. Helens | 1.8 |
| Sutton Manorbattery storage | battery storage | 57 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Sep 2022 | Jun 2022 | St. Helens | 2.2 |
| College Streetrooftop solar | rooftop solar | 1.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | St. Helens | 2.8 |
| Land South Of Joy Lanesolar farm | solar farm | 5 | refusedupdated Sep 2015 | May 2015 | refused Aug 2015 | Sep 2015 | Warrington | 4.6 |
| Lockheed Road, Burtonwood & Westbrookrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Warrington | 4.6 |
| The Hut Group, Skyline Driverooftop solar | rooftop solar | 6.8 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Warrington | 4.8 |
| The Hut Group, Skyline Driverooftop solar | rooftop solar | 1.5 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Warrington | 4.8 |
| Amazon Omega Business Parkrooftop solar | rooftop solar | 1.5 | operationalupdated Jan 2020 | Feb 2019 | granted Apr 2019 | Jan 2020 | Warrington | 5.1 |
| Fairchild Road, Burtonwood & Westbrookrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Oct 2023 | Nov 2023 | Warrington | 5.3 |
| Causeway Bridges Wind Farmwind farm | wind farm | 4 | abandonedupdated Jul 2014 | Apr 2008 | granted May 2008 | Jul 2014 | Warrington | 6.6 |
| Mowcroft Solar Farmsolar farm | solar farm | 27.1 | refusedupdated Dec 2025 | Jul 2025 | refused Oct 2025 | Dec 2025 | Warrington | 6.8 |
| Fiddlers Ferry Power Stationbattery storage | battery storage | 150 | under constructionupdated Mar 2024 | Jul 2022 | granted Jun 2023 | Mar 2024 | Warrington | 7.3 |
| Mill Farmsolar farm | solar farm | 5 | abandonedupdated Dec 2018 | Jul 2015 | granted Dec 2015 | Dec 2018 | Wigan | 7.7 |
| Land south of 50 Station Roadsolar farm | solar farm | 5 | refusedupdated Sep 2015 | May 2015 | refused Aug 2015 | Sep 2015 | Warrington | 7.7 |
| Johnson's Lane - Haltonsolar farm | solar farm | 3.5 | abandonedupdated Jun 2019 | Jun 2015 | granted Oct 2015 | Jun 2019 | Halton | 7.8 |
| Johnson's Lane - Warringtonsolar farm | solar farm | 1.5 | abandonedupdated Jun 2019 | Jun 2015 | granted Feb 2016 | Jun 2019 | Halton | 8.0 |
| Station Road, Fiddlers Ferrybattery storage | battery storage | 250 | refusedupdated Dec 2025 | Jul 2025 | refused Dec 2025 | Dec 2025 | Warrington | 8.0 |
| Holiday Moss Landfill Site, Reeds Browbattery storage | battery storage | 3 | approved, not built may be out of dateupdated Dec 2022 | Sep 2022 | granted Nov 2022 | Dec 2022 | St. Helens | 8.4 |
| Promised Land Farmwind farm | wind farm | 1 | operationalupdated Feb 2017 | May 2013 | granted Oct 2013 | Feb 2017 | St. Helens | 8.5 |
| Cut Lanebattery storage | battery storage | 57 | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | Knowsley | 8.5 |
| Sandyforth Farm, Ashton Roadbattery storage | battery storage | 70 | approved, not builtupdated Apr 2025 | Feb 2024 | granted Feb 2025 | Apr 2025 | Wigan | 8.7 |
| St Michaels Road, Ditton Roadbattery storage | battery storage | 14 | approved, not builtupdated Nov 2023 | Nov 2022 | granted Oct 2023 | Nov 2023 | Halton | 9.1 |
| Ditton Road Solar Microgridsolar farm | solar farm | 4 | approved, not builtupdated Feb 2026 | Jun 2024 | granted Jan 2025 | Feb 2026 | Halton | 9.2 |
| Poundland Distribution Centre,Three Sisters Roadrooftop solar | rooftop solar | 2.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Wigan | 9.3 |
| Coopers Lane, Kirkbybattery storage | battery storage | 49.5 | approved, not builtupdated May 2024 | Jul 2023 | granted Apr 2024 | May 2024 | Knowsley | 9.4 |
| Warrington Home Solar Schemerooftop solar | rooftop solar | 5.3 | operationalupdated Jul 2016 | — | — | Jul 2016 | Warrington | 9.4 |
| Hedco, Desoto Roadsolar farm | solar farm | 3.5 | approved, not builtupdated May 2026 | May 2022 | granted Jun 2024 | May 2026 | Halton | 9.5 |
| Perimeter Road, Kirkbybattery storage | battery storage | 165 | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Knowsley | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (31)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| DTC St Helens Hospital, Marshalls Cross Roadrooftop solar | rooftop solar | 0.2 | refusedupdated May 2024 | Mar 2024 | refused May 2024 | May 2024 | St. Helens | 0.5 |
| Arnold Clark Renault, Delphwood Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | St. Helens | 1.0 |
| St Helens Rugby League Stadium, Peasley Cross Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2023 | Nov 2022 | granted Jan 2023 | Mar 2023 | St. Helens | 1.2 |
| The Sutton Academy, Elton Head Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | St. Helens | 1.3 |
| Mere Grange, Leasiderooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted Jun 2025 | Jun 2025 | St. Helens | 1.7 |
| Lea Green Business Park, Eurolinkrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | St. Helens | 2.4 |
| Lea Green Business Park, Eurolinkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | St. Helens | 2.4 |
| Queens Park Health And Fitnessrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | St. Helens | 2.9 |
| Omega West, St Helens, Unit 4, Zone 8rooftop solar | rooftop solar | 0.7 | application withdrawnupdated Feb 2025 | Nov 2024 | — | Feb 2025 | St. Helens | 4.5 |
| City Plumbing, Lockheed Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Warrington | 4.6 |
| Whiston Hospital, Warrington Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Oct 2025 | granted Dec 2025 | Apr 2026 | Knowsley | 4.7 |
| Bellerophon Way Tescorooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Sep 2020 | Mar 2019 | granted May 2019 | Sep 2020 | St. Helens | 4.8 |
| Dominos Pizza, Skyline Driverooftop solar | rooftop solar | 1 | approved, not builtupdated Feb 2023 | Jan 2023 | granted Feb 2023 | Feb 2023 | Warrington | 5.0 |
| Haweswater Car Park Solar Canopysolar farm | solar farm | 0.9 | approved, not builtupdated Oct 2024 | May 2024 | granted Oct 2024 | Oct 2024 | Warrington | 5.1 |
| Starbank Panel Products, Junction Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | St. Helens | 5.2 |
| Rivendell Nurseriesrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Halton | 5.3 |
| Enviropax, Hall Wood Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | St. Helens | 6.0 |
| Newton Le Willows Health And Fitnessrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | St. Helens | 6.8 |
| Arnold Clark Automobiles, Europa Boulevardrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2024 | May 2025 | Warrington | 6.8 |
| Earlsfield Park, Arley Driverooftop solar | rooftop solar | 0.1 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Knowsley | 7.1 |
| Sutton International, Gorsey Lane Solar PV Arraysrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Halton | 7.9 |
| Units 2-4 Opus 9 Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Warrington | 8.1 |
| Christeyns Food Hygiene, Cameron Courtrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Dec 2024 | Jan 2025 | Warrington | 8.1 |
| Warrington Teaching Hospital, Lovely Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | Warrington | 8.6 |
| Beamont Collegiate Academy, Long Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | Warrington | 9.2 |
| Halliwell Jones Stadium, Winwick Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Warrington | 9.3 |
| Peter Gilding And Company, Caddick Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Dec 2024 | Dec 2024 | Knowsley | 9.7 |
| Adlib House, Kitling Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Sep 2023 | Oct 2023 | Knowsley | 9.8 |
| Pembroke Court, Haltonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Halton | 9.9 |
| Penrhyn Court, Penrhyn Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Jan 2026 | granted Feb 2026 | May 2026 | Knowsley | 10.0 |
| Beverston Engineering, Unit Brooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Knowsley | 10.0 |
Distance from the average position of the WA9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 0 | 3 | 0 | 3 | 8.4 |
| Rooftop solar | 38 | 2 | 32 | 2 | 1 | 23.6 |
| Wind farm | 2 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 11 | 2 | 7 | 0 | 1 | 566 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 31.4 |
| Burbo Bank Extension (Burbo Bank 2) | 258 | operationalupdated May 2018 | 36.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How St. Helens decides solar, wind and battery applications
| Applications | St. Helens | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 1 of 13 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 7.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WA9, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.