Energy Projects Near You

Renewable energy projects in St. Helens

19 solar, wind or battery projects of 150 kW or more are located in St. Helens (REPD, July 2026 extract): 0 pending, 15 approved but not running, 1 operational and 1 refused. The council refused 1 of 17 decided applications (6%; UK 19%), with a median 8 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects in the council area
0awaiting a decision
15approved, not running
6%of decisions refused

How St. Helens decides

ApplicationsSt. HelensUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused1 of 1312%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision7.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in St. Helens

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Sutton Manorbattery storagebattery storage57approved, not built may be out of dateupdated Jun 2022Jun 2022granted Sep 2022Jun 2022
Burtonhead Roadbattery storagebattery storage30abandonedupdated Feb 2019Oct 2017—Feb 2019
Holiday Moss Landfill Site, Reeds Browbattery storagebattery storage3approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022
College Streetrooftop solarrooftop solar1.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024
Promised Land Farmwind farmwind farm1operationalupdated Feb 2017May 2013granted Oct 2013Feb 2017
Biffa Electricity Generating Compound, Burtonhead Roadbattery storagebattery storage1approved, not built may be out of dateupdated Nov 2022Aug 2022granted Oct 2022Nov 2022
Smaller schemes under 1 MW, mostly rooftop solar (13)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Omega West, St Helens, Unit 4, Zone 8rooftop solarrooftop solar0.7application withdrawnupdated Feb 2025Nov 2024—Feb 2025
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.6approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024
Starbank Panel Products, Junction Lanerooftop solarrooftop solar0.5approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022
Bellerophon Way Tescorooftop solarrooftop solar0.4approved, not built may be out of dateupdated Sep 2020Mar 2019granted May 2019Sep 2020
St Helens Rugby League Stadium, Peasley Cross Lanerooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Nov 2022granted Jan 2023Mar 2023
The Sutton Academy, Elton Head Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025
Queens Park Health And Fitnessrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025
Newton Le Willows Health And Fitnessrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025
Mere Grange, Leasiderooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025
DTC St Helens Hospital, Marshalls Cross Roadrooftop solarrooftop solar0.2refusedupdated May 2024Mar 2024refused May 2024May 2024
Enviropax, Hall Wood Avenuerooftop solarrooftop solar0.2approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026
Arnold Clark Renault, Delphwood Driverooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026

Postcode districts in St. Helens

DistrictProjects within 10 kmPendingApprovedOperational
WA9604423
WA10609373
WA11658443
WA12582403

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to St. Helens by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.