Sandyforth Farm, Ashton Road (70 MW battery storage)

Sandyforth Farm, Ashton Road is a 70 MW battery storage project in Wigan, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 February 2025, not yet built; the record was last updated on 1 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWbattery storage
approved, not builtstatus in REPD
1 April 2025record last updated
Wigancouncil area

Planning timeline

DateStage
7 February 2024Application submitted
25 February 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
70 MW
Status (REPD)
approved, not built
Record last updated
1 April 2025
Operator or applicant
UKGEA
Planning authority
Wigan
Planning application reference
A/23/96568/MAJOR
Address (REPD)
Sandyforth Farm, Ashton Road, Billinge, Wigan
Council area (by location)
Wigan
Time to decision
55 weeks
Name in REPD
Sandyforth Farm, Ashton Road - Battery Energy Storage
REPD reference
15930

Who decides

ApplicationsWiganUK
Decided applications (solar, wind, battery)1710,236
Refused0 (0%)19%
Solar refused0 of 1312%
Battery storage refused0 of 416%
Median time from submission to decision9.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mill Farmsolar farm5abandoned2.2
Kilshaw Streetbattery storage20permission expired2.6
Far Moorbattery storage50application submitted3.1
Tontine Roadbattery storage70application submitted3.8
Orrell Street Battery Energy Storage Facilitybattery storage50approved, not built5.1
Pikelaw Placebattery storage10permission expired6.2
Burtonhead Roadbattery storage30abandoned8.3
Thompson House Equestrian farmsolar farm5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5108, -2.6825).