Solar, wind and battery projects near Wigan (WN5)
39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WN5 (Wigan): 5 are waiting for a planning decision, 25 approved but not yet running, 6 operational. The largest live scheme is Avondale Nurseries, Spa Lane (320 MW battery storage, approved on 23 July 2025, not yet built), 9.9 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 33.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WN5
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Kilshaw Streetbattery storage | battery storage | 20 | permission expiredupdated Jul 2020 | Oct 2017 | granted Mar 2019 | Jul 2020 | Wigan | 0.8 |
| Far Moorbattery storage | battery storage | 50 | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | West Lancashire | 2.1 |
| Tontine Roadbattery storage | battery storage | 70 | application submitted may be out of dateupdated Oct 2021 | Jan 2023 | — | Oct 2021 | West Lancashire | 2.3 |
| Sandyforth Farm, Ashton Roadbattery storage | battery storage | 70 | approved, not builtupdated Apr 2025 | Feb 2024 | granted Feb 2025 | Apr 2025 | Wigan | 2.4 |
| Promised Land Farmwind farm | wind farm | 1 | operationalupdated Feb 2017 | May 2013 | granted Oct 2013 | Feb 2017 | St. Helens | 4.0 |
| Orrell Street Battery Energy Storage Facilitybattery storage | battery storage | 50 | approved, not builtupdated Jun 2026 | Aug 2023 | granted Feb 2026 | Jun 2026 | Wigan | 4.3 |
| Mill Farmsolar farm | solar farm | 5 | abandonedupdated Dec 2018 | Jul 2015 | granted Dec 2015 | Dec 2018 | Wigan | 4.4 |
| Poundland Distribution Centre,Three Sisters Roadrooftop solar | rooftop solar | 2.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Wigan | 4.7 |
| Barton House Farm, Pimbo Roadwind turbine | wind turbine | 2.5 | approved, not builtupdated Jun 2026 | Jan 2025 | granted Apr 2026 | Jun 2026 | West Lancashire | 5.2 |
| Pikelaw Placebattery storage | battery storage | 10 | permission expiredupdated Aug 2020 | May 2017 | granted Jul 2017 | Aug 2020 | West Lancashire | 5.3 |
| Holiday Moss Landfill Site, Reeds Browbattery storage | battery storage | 3 | approved, not built may be out of dateupdated Dec 2022 | Sep 2022 | granted Nov 2022 | Dec 2022 | St. Helens | 5.6 |
| Thompson House Equestrian farmsolar farm | solar farm | 5 | operationalupdated Nov 2016 | Oct 2014 | granted Feb 2015 | Nov 2016 | Wigan | 7.3 |
| Unit 5 XL Business Parkbattery storage | battery storage | 49.9 | under constructionupdated Jun 2020 | Sep 2017 | granted Dec 2017 | Jun 2020 | West Lancashire | 8.6 |
| College Streetrooftop solar | rooftop solar | 1.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | St. Helens | 8.6 |
| Vause Farmbattery storage | battery storage | 20 | approved, not builtupdated Feb 2024 | Mar 2022 | granted Feb 2024 | Feb 2024 | Chorley | 9.2 |
| Charnock Richardbattery storage | battery storage | 30 | operationalupdated Mar 2026 | Feb 2022 | granted May 2022 | Mar 2026 | Chorley | 9.2 |
| Avondale Nurseries, Spa Lanebattery storage | battery storage | 320 | approved, not builtupdated Aug 2025 | Dec 2024 | granted Jul 2025 | Aug 2025 | West Lancashire | 9.9 |
| Lathom (Pilkington Technical Centre)solar farm | solar farm | 2.5 | operationalupdated May 2019 | Apr 2018 | granted Jul 2018 | May 2019 | West Lancashire | 9.9 |
| Lathom (Pilkington Technical Centre) Battery Storagebattery storage | battery storage | 2 | operationalupdated Aug 2020 | Apr 2018 | granted Aug 2018 | Aug 2020 | West Lancashire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Systems Glassrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2022 | Mar 2022 | granted Apr 2022 | Apr 2022 | Wigan | 2.5 |
| Robin Park Leisure Centre, Loire Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | Wigan | 2.6 |
| Wigan Investment Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2021 | Jun 2021 | granted Aug 2021 | Jul 2021 | Wigan | 3.5 |
| Westgate House, Green Streetrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Wigan | 3.9 |
| Wigan Youth Zonerooftop solar | rooftop solar | 0.2 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Wigan | 3.9 |
| Royal Albert Edward Infirmary, Wigan Lanerooftop solar | rooftop solar | 0.2 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Wigan | 4.8 |
| St Francis Of Assisi Catholic Primary Schoolrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | West Lancashire | 4.9 |
| Pimbo Road, By Paxton Place Jnct - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | application submitted | Apr 2026 | — | — | West Lancashire | 5.2 |
| Hannah Food Services, Garnett Placerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | West Lancashire | 6.4 |
| West Lancashire College, College Way -Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Oct 2024 | Nov 2024 | West Lancashire | 6.5 |
| Enviropax, Hall Wood Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | St. Helens | 6.6 |
| Wrightington Hospital, Hall Lanerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 | West Lancashire | 6.6 |
| Bradley Hall Trading Estate, Bradley Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 | Wigan | 7.3 |
| Bellerophon Way Tescorooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Sep 2020 | Mar 2019 | granted May 2019 | Sep 2020 | St. Helens | 7.6 |
| Sanko Gosei Solar Panelsrooftop solar | rooftop solar | 0.5 | operationalupdated Sep 2022 | Dec 2020 | granted Feb 2021 | Sep 2022 | West Lancashire | 8.0 |
| Newton Le Willows Health And Fitnessrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | St. Helens | 9.0 |
| Scot Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2026 | Aug 2025 | granted Jan 2026 | Mar 2026 | Bolton | 9.3 |
| Queens Park Health And Fitnessrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | St. Helens | 9.5 |
| St Helens Rugby League Stadium, Peasley Cross Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2023 | Nov 2022 | granted Jan 2023 | Mar 2023 | St. Helens | 9.8 |
| Starbank Panel Products, Junction Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | St. Helens | 9.8 |
Distance from the average position of the WN5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 0 | 2 | 0 | 0 |
| Rooftop solar | 20 | 2 | 17 | 1 | 0 | 8.2 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 2.5 |
| Battery storage | 14 | 3 | 7 | 2 | 0 | 633 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 33.2 |
| Burbo Bank Extension (Burbo Bank 2) | 258 | operationalupdated May 2018 | 38.9 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Wigan decides solar, wind and battery applications
| Applications | Wigan | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 9.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WN5, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.