Energy Projects Near You

Orrell Street Battery Energy Storage Facility (50 MW)

Orrell Street Battery Energy Storage Facility is a 50 MW battery storage project in Wigan, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 February 2026, not yet built; the record was last updated on 15 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
15 June 2026record last updated
Wigancouncil area

Planning timeline

DateStage
29 August 2023Application submitted
26 February 2026Planning permission granted
26 February 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
15 June 2026
Operator or applicant
Enzygo Limited Environmental Consultants
Planning authority
Wigan
Planning application reference
A/23/95931/MAJOR
Address (REPD)
Site Of Former Council Depot Orrell Street
Council area (by location)
Wigan
Time to decision
130 weeks
REPD reference
14892

Earlier applications for this site

ApplicationMWSubmittedOutcome
Orrell Street Battery Energy Storage Facility A/20/88858/MAJOR—12 March 2020replaced by a revised application

Who decides

ApplicationsWiganUK
Decided applications (solar, wind, battery)1710,236
Refused0 (0%)19%
Solar refused0 of 1312%
Battery storage refused0 of 416%
Median time from submission to decision9.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilshaw Streetbattery storage20permission expired3.5
Sandyforth Farm, Ashton Roadbattery storage70approved, not built5.1
Mill Farmsolar farm5abandoned5.5
Tontine Roadbattery storage70application submitted6.4
Far Moorbattery storage50application submitted6.4
Slack Lane, Westhoughtonbattery storage45approved, not built7.2
Thompson House Equestrian farmsolar farm5operational7.4
Athertonbattery storage30operational8.1
Vause Farmbattery storage20approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5411, -2.6247).